2011-19 TASK ORDER NUMBER 03 TO AGREEMENT FOR ENGINEER SERVICES
ON A CONTINUING BASIS
THIS AGREEMENT is made as of the O TAI day of 4pLi / in the year 2011,
between the CITY OF CLERMONT, a Florida Municipal Corporation, whose address is, 685
West Montrose Street, Clermont, Florida 34711 (hereinafter referred to as the "CITY "), and
AECOM TECHNICAL SERVICES, INC., whose address is 150 NORTH ORANGE AVNEUE,
SUITE 200, ORLANDO, FLORIDA 32801, (hereinafter referred to as the "ENGINEER ")
WITNESSETH:
WHEREAS, on October 13, 2009 the CITY and the ENGINEER, previously entered
into an Agreement for ENGINEER Services on a Continuing Basis (hereinafter referred to as the
"Agreement "). The Agreement is referenced herein as though set forth in full.
WHEREAS, the CITY and the ENGINEER desire to enter into a Written Amendment
for Task Order Number 03.
NOW THEREFORE, for and in consideration of the mutual covenants and promises
contained in this Agreement, the CITY and the ENGINEER do hereby agree as set forth below:
1. The above recitals are true and correct and are incorporated herein.
2. The Parties agree to the scope of work and budget pursuant to the terms and conditions set
forth in Exhibits "A & B."
IN WITNESS WHEREOF, the parties hereto have executed this Agreement on the
respective dates under each signature.
"ENGINEE : B Ardita
Y
, ant, DiV•T President
Dat 3 /o //,
"CITY"
Attest: �� _ /
i �:
Date: Air_
t „: 4,, , L ��4
q R CEIVED
- 11
EXHIBIT A
TASK AUTHORIZATION 03
SCOPE OF WORK FOR
CUP APPLICATION RENEWAL RESPONSE TO RAI #6
BACKGROUND
This Scope of Services is Task Order No. 3 pursuant to the Engineering Consulting Services
Agreement dated October 13, 2009 between the City of Clermont (CITY) and AECOM Technical
Services, Inc. (ENGINEER).
The City of Clermont was issued a Consumptive Use Permit (CUP) #2478 on September 10,
2002, for a 20 -year duration, along with 54 Conditions of Issuance. The water allocations for
CUP #2478 are subdivided into the East and West Service Areas and have specific targets and a
drastic 51% "Step" reduction in the year 2013 from 7.378 -mgd to 3.776 -mgd. The following is
the timeframe of the CUP renewal application.
• In January 2007, ENGINEER on behalf of the CITY submitted the CUP modification
application to the St. Johns River Water Management District (SJRWMD).
• In February 2007, SJRWMD responded with Request for Additional Information #1 (RAI
#1) totaling twenty -six (26) comments with particular focus on confirming population
projections with the SJRWMD's population projection consultant (GIS Associates).
ENGINEER received the confirmed population projections from GIS Associates in
December 2007 and then submitted the response to RAI #1 in January 2008.
• In February 2008, SJRWMD responded with RAI #2 totaling twenty-four (24) comments
with focus on the CITY's East and West Service Areas projected water use reductions per
capita and projected water supply sources limiting additional groundwater withdrawal
beyond 2013. ENGINEER reformatted projections to show per capita reductions and
received SJRWMD concurrence in December 2008. ENGINEER submitted the response
to RAI #2 in January 2009.
• In February 2009, SJRWMD responded with RAI #3 totaling eight (8) new additional
comments with focus on demonstration of need and water conservation. ENGINEER
submitted the response to RAI #3 in June 2009.
• In June 2009, SJRWMD responded with RAL #4 totaling six (6) new additional
comments with focus on demonstration of need, water conservation and environmental
resource impacts. ENGINEER submitted the response to RAI #4 in April 2010.
• In June 2010, SJRWMD responded with RAI #5 totaling thirteen (13) new additional
comments with focus on demonstration of need, reuse, water conservation and
environmental resource impacts. ENGINEER submitted the response to RAI #5 in
November 2010.
• In December 2010, SJRWMD responded with RAI #6 totaling fourteen (14) new
comments with emphasis on the demonstration of need, reuse implementation, and
environmental resource impacts. The purpose of this scope of work is to provide services
to respond to RAI #6. SJRWMD requested the response be submitted by April 15 2011.
Scope of Services
The purpose of this scope is to provide services to respond to RAI #6. The ENGINEER and
subconsultant hydrogeologist, Connect Consulting, Inc. (CCI) and surveyor, Rapid Surveying
Inc., (RSI) will perform the following tasks to respond RAI #6 with the assistance from the
CITY.
Task 1 Project Management, Invoicing and Meetings
1.1 Prepare project status and invoicing reports (limit 2).
1.2 Prepare for and attend progress meetings with CITY to present the initial findings
and progress on RAI #6 responses (limited to two (2) meetings).
1.3 Prepare for and attend progress meetings with SJRWMD to present the initial
findings and progress on RAI #6 responses (limited to two (2) meetings).
Task 2 Response to RAI #6 Comments
SJRWMD issued fourteen (14) RAI comments associated with three (3) areas of concern. Table
1 presents the RAI comment and responsible party for addressing each area of concern for RAI
#6. The following tasks are relative to each area of concern:
Demonstration of Need
2.1 Create a summary table for Table 2 Projected Water Use and Supply similar to the
table provided by the District. (AECOM)
Reuse
2.2 Provide reclaimed water implementation schedule that includes golf courses.
(AECOM)
Environmental and Resource Impacts
2 3 Confirm and submit new model files to the District. (CCI, Included in Task 2.14)
2.4 Update public supply landscape irrigation for subdivisions not expected to receive
reclaimed water by 2013 in model. (CCI, Included in Task 2.14)
2.5 Revise the "Recharge Calcs Table" in recharge package for 2013. (CCI, Included
in Task 2.14)
2.6 Corroborate Recharge Calcs Table, and CITY's RIB application rates with the
City's projected water use for 2013. (CCI)
2 7 Confirm the proposed withdrawal rate for Well #33694 and revise model for 2013
and water use projection tables accordingly (CCI, Complete)
2.8 Provide a summary of flux changes across the western boundary of the SJRWMD
ECF Model. (CCI, Complete)
2.9 Summarize the CITY's existing wetland and surface water monitoring data in
order to assist the CITY to provide assurances that there have been no adverse
impacts to surface waters and wetlands as a result of the current permitted
withdrawals.
2.9.1 Update the stage duration curves for the six locations where hydrologic
monitoring data is collected by the CITY. (ENGINEER)
2.9.2 Compare ecological indicators of long term hydrology with the stage
duration curves at each of the six (6) monitoring locations to evaluate if
current groundwater withdrawls have resulted in observable impacts.
ENGINEER will establish a transect at each monitoring site and locate the
elevations of visible ecological indicators along the transect. Elevations
will be located by a licensed surveyor (RSI). The ecological indicators
may include: cypress inflection points, adventitious roots, water stain
lines, edge of saw palmetto line, top of organic soils 6" in depth, top of
organic soil 16" in depth, top of moss collars, and lower edge of lichen
lines. Not all indicators may be present at all sites. (RSI/ENGINEER)
2.10 Investigate the CITY's six (6) existing piezometers to determine if wells were
constructed deep enough to measure low water levels or if new wells need to be
constructed to document low water levels. Specifically, well construction reports
provided by the CITY will be compared with the water level data from
groundwater monitoring wells: Jacks Lake (2478 -PZ3), Lake Apshawa (2478 -
PZ4), Lake Felter (2478 -PZ5), US27 South (2478 -PZ6). (CITY/ENGINEER)
2.11 Conduct a Wetland and Surface Water Impact Analysis to assist the CITY to
provide reasonable assurance that there will be no adverse impacts to surface
waters and wetlands as a result of the proposed withdrawals for the permit
duration for two scenarios: the City Only and the Cumulative. This analysis is
largely a desk top exercise using GIS databases and existing literature. Tasks
include:
2.11.1 Figures depicting drawdown in the surficial aquifer based on the CITY's
proposed withdrawals alone using contour intervals of 0.2 -foot (starting at
0.1). Scale figures to focus on the CITY's zone of influence and relevant
landscape features. (CCl/ENGINEER)
2.11.2 Figures depicting cumulative drawdown in the surficial aquifer based on
the CITY's proposed withdrawals plus permitted and pending withdrawals
using contour intervals of 0.2 -foot (starting at 0.1). Scale figures to focus
on the CITY's zone of influence and relevant landscape features.
(CCl/ENGINEER)
2.11.3 Figures depicting the City Only and the cumulative drawdowns in the
surficial aquifer overlaid on a base map depicting wetlands /surface waters
within CITY's zone of influence. (CCl/ENGINEER)
2.11.4 Assessment of potential impact to wetlands /surface waters in the CITY' s
zone of influence due to the CITY's withdrawals only and due to
cumulative groundwater model withdrawal. The assessment will include
descriptions of wetland / surface water habitats, based on the soils,
vegetation, and hydrology, and an assessment for the potential level of
harm for each system. (ENGINEER)
2.11.5 The wetland/surface water assessment will include an assessment of the
current monitoring plan, and will evaluate the need for additional
monitoring sites. (ENGINEER)
2.12 Assist the CITY to explain how the CITY will minimize potential impacts to
surface waters and wetlands during the duration of the permit. ENGINEER will
assist the CITY describe the current proposed withdrawal schedules and how to
reduce impacts. (CITY/ENGINEER)
2.13 Revise drawdown data for lakes with established MFL based on revised model
including:
a) List MFL water bodies in Lake, Orange and Seminole Counties (CCI)
b) Cumulative Drawdown (CCI)
c) Drawdown Limit (CCI)
d) Percent Contribution of Project Only drawdown to Cumulative drawdown
(CCI)
2.14 Revise model data for springs with established minimum flows or screening
levels including:
a) List springs included in the ECF model (CCI)
b) Estimated actual annual 1995 flow(CCI)
c) Simulated 1995 flow as reported by the SJRWMD (CCI)
d) Simulated flow for modeled scenarios (City Only, Cumulative) (CCI)
e) Difference and percent difference in simulated flow as compared to
simulated 1995 flow (CCI)
f) Minimum flow or screening flow (CCI)
Task 3 Prepare Response Letter to RAI #6 Comments
3.1 Prepare draft letter response for RAI #6 for QC review prior to submittal to
SJRWMD.
3.2 Submit final letter response for RAI #6 to SJRWMD.
3.3 Prepare for and attend a strategy meeting with CITY to review and strategize
response for RAI #7 (if needed).
CITY'S RESPONSIBILITIES
The CITY will provide the information and services described in Table 1.
• Access to monitoring locations.
• Copies of monitoring well construction reports, survey, and stage data.
The ENGINEER will be entitled to rely upon the above direction, information, and documents
provided by the CITY without independent review or verification.
SERVICES NOT INCLUDED
The following sections will be excluded from the RAI #6 response until the SJRWMD concurs
with the projected demands. At that time, the CITY shall direct the ENGINEER that the
excluded sections are to be added to the scope of work and additional compensation for the
excluded sections will be determined.
1. Wetland or other field investigations not described in this scope.
2. Specific wetland or surface water mitigation plans.
3. Review of alternative sources of potable water. Should the District request the CITY to
pursue alternative water (such as a supplemental surface water supply for potable water
use), the work will be completed by a separate scope of services as an Additional Service.
4. No budget included for future RAIs.
5. Permitting fees
DELIVERABLES
The ENGINEER will submit four (4) signed and sealed response letters to RAI #6 and
supplemental information to the SJRWMD on behalf of the CITY.
TABLE 1: RAI #6 Comments Response Strategy for CUP #2478
Comment Abbreviated Task Description Responsibility Status
1 ❑ Create a summary table for Table 2 Projected ENGINEER Complete
Water Use and Supply
2 ❑ Provide reclaimed water implementation ENGINEER Complete
schedule
3 ❑ Confirm and submit new model files to the CCI Complete
District.
4 ❑ Update public supply landscape irrigation for CCI Revise/Update
by 2013 in model Model
5 ❑ Revise recharge package for 2013. CCI Revise/Update
Model
6 ❑ Corroborate Recharge Calcs Table, and CCI Revise/Update
CITY 's RIB application rates with the CITY Model
projected water use for 2013
7 ❑ Confirm the proposed withdrawal rate for CCI Complete
Well #33694
---- - - - - --
8 ❑ Evaluate boundary affects on the SJRWMD CCI Complete
ECF Model
9 ❑ Evaluate impact of current withdrawals on ENGINEER Desk -top / Field
wetlands and surface waters Work
10 ❑ Investigate well construction of piezometers CITY/ ENGINEER Desk -top / Field
Work
11 ❑ Evaluate impact of proposed withdrawals on ENGINEER Desk -top / Field
wetlands and surface waters Work
12 ❑ Assist the CITY to explain how the CITY CITY/ENGINEER Desk -top
will minimize potential impacts to surface
waters and wetlands during the duration of
the permit
13 ❑ Revise drawdown data for lakes with MFL CCI Revise/Update
Model
14 ❑ Revise model data for springs with screening CCI Revise/Update
levels Model
SCHEDULE
Services pursuant to this Scope of Services will commence upon ENGINEER's receipt of
Purchase Order from CITY. It is anticipated that a response letter to RAI #6 will be prepared and
submitted within 120 days from Notice To Proceed (NTP), assuming timely delivery of CITY's
data.
ENGINEER will observe the time limitations; however, should there be delays in receiving
information from others and in obtaining subsequent authorization, approvals, and review
comments from the CITY, and other governmental agencies, the schedule will be updated and
adjusted as mutually agreed upon by ENGINEER and CITY. ENGINEER shall not be
responsible for delays that occur as the result of action or inaction of CITY or others.
COMPENSATION
This Scope of Services establishes a total not -to- exceed cost of $52,850 for services described
herein. This fee was determined based on the assumptions presented herein and in the attached
Project Budget. The fee breakdown is apportioned in Project Budget (Exhibit 1). Progress
payments shall be due and payable on a monthly basis.
SUBCONSULTANT
Hydrogeologic modeling services are to be provided by Connect Consulting, Inc (CCI).
ENGINEER survey will be provided by Rapid Survey Inc, (RSI). Services to be provided by
CCI and RSI are incorporated in to the scope of services budget and are presented in Exhibit 2
for reference.
AUTHORIZATION
This Task Order No. 03 serves as an Exhibit to the Consultant Agreement dated October 13,
2009, between the City of Clermont and AECOM Technical Services, Inc., and is hereby
incorporated into this Amendment by reference.
Attachments: Exhibit 1 Project Budget
Exhibit 2 Subconsultants fee proposals.
EXHIBIT 1
Project Budget
Task Order #3
Response to CUP RAI #6 City of Clermont
Personnel Hours Budget
l
U
Task Description i i _ 2 e 3 o
7 Q - C < . o a m °
r i U < • it z
Task Group 1 Protect Management, Invoicing and Meetings
1 1 Project management status and ms oicmg reports Omit 2) 2 4 4 10 S 1,240 S 175 S 1 415
1 2 Prepare for and attend meetings with SJRWVID (Lumt two (2) meetings) 4 8 2 14 5 1 740 S 175 S 1 915
1 3 Prepare for and Attend meetings with City (Lout two (2) mecmgs) 4 8 2 14 S 1 740 5 180 S 1 920
Subtotal 2 12 16 - - 8 38 5 4,720 5 - S 530 S 5,250
Task Group 2 Response to RAI #6Comments
Demonstration of Need - $ - S - S. -
2 1 Create a summary table for Table 2 Projected R ater Use and Supply
(Complete) - 5 - 5 - 5 -
2 2 Provide reclaimed nater implementation schedule (Complete) - S - 5 $ -
Reuse - S - 5 - 5
2 3 Confirm and submit new model files to the Dtsbtct (Included in Task 2 14) - S - 5 - 5 -
Envvonmeutal and Resource Impacts - S - $ - 5 -
2 4 Lpdate pubhc supply landscape irrigation for by 2013 in model (Included m
Task 2 14) - 5 - S -
2 5 Rnsse recharge package for 2013 (Included m Task 2 14) - 5 S -
2 6 Corroborate Recharge Caks Table and City's RID application rates with the
Can's projected water use for 2013 (included m Task 2 14) - 5 - $ -
2 7 Confirm die proposed withdrawal rate for R el 933694 (Complete) - S - 5 -
2 6 Evaluate boundary affects on the SJRWVID ECF Model (Complete) - 5 - $ -
2 9 Evaluate impact of current wvhdrawals on w etland and surface w eters 2 8 40 28 16 2 96 S 10 600 S 6 000 5 250 S 16 S50
2 10 Investigate w e8 construction of ptezometers 4 10 10 24 S 2 710 5 150 S 2 860
2 11 Evaluate mrpact of proposed wvhdraw als on n etland and surface meters 2 8 40 28 10 2 90 5 10 090 S 220 5 10 310
2 12 Descnbe plan to mm®sae potential mmams to surface w aters 8 4 4 16 S 1 980 S 1 900
2 13 Rnsse draw down data for lakes wnh MFL (Included m Task 2 14) - 5 - S
2 14 Revise model data for springs with screening In els - S - S 5 000 S 5 000
Subtotal 4 28 94 70 26 4 226 5 25,380 S 11,000 5 620 S 37,000
Task Group 3 Prepare Response Letter to RAI #6
3 1 Prepare draft letter response for QC Anew 4 8 16 16 4 2 50 S 5 840 S 580 5 6 420
3 2 Sub letter response to SJRNVID 2 4 6 8 2 1 25 S 2 920 S 290 $ 3 210
3 3 Prepare for and attend strategy meeting oath City for RAI =6 response 2 4 1 7 S 870 S 100 5 970
- S - S -
- 5 5 -
Subtotal 6 14 28 24 6 4 82 S 9,630 S $ 970 S 10,600
Total 12 54 138 94 32 16 346 S 39,730 S 11,000 $ 2,120 S 52,850
EXHIBIT 2:
SUBCONSULTANT FEE PROPOSALS
t CCI 19505 NW 184th Terrace
High Springs, FL 32643
Proposal
Phone: 561 249.6778 Proposal Date
Fax 386 562.0059
2r24f2011
Robb_e Ganwlav, P E
AECOM
320 East Sonh St
Orlando. FL 32911
P O NO Project
Descnptwn Qua Una Cost Total
Update Clemons Gaoled Water Flow Model to account fax Recharge at 2013 m response to RAI
Remselupdate Model 1 5 000 00 5.000.00
Thm.%you fa: your business
Total S5 000 00
email gerchlerlix.netcorn.com
RAPID SURVEYING INC.
Larry Bowen, President
2010 W WINTER LAKE ROAD OFFICE (863) 668 -9124
LAKELAND, FL 33803 FAX (863) 668 -9001
P OBOX 239 CELL (863) 412-1660
EATON PARK, FL 33840 E -MAIL lan-varapadsurvevana net
Website: r1.ww_rap3dsurveying_net
PROPOSAL LETTER
For Specific Purpose Survey
March 7, 2011 Proposal Letter No a1659
Mike E-lowe
AECOM
150 North Orange Avenue. Suite 200
Orlando, FL 32801
RE. Clermont C LI P.
Dear Mr. Hove:
Thank you for alibwtng Rapid Surveying. Inc. (RSI) the opportunity to present this proposal for this project We
can complete the `Surrey Scope of Services'. in a timely fashion upon return of the signed proposal Iet'er
Project limits of proposed surveying scope of services
Hatched areas depicted on attachment 'A' Supplied by client
Survey scope of services:
1. Specific Purpose Survey
a Provide Transect lines at 6 separate sites per marked location on attachment °A'
2 Survey Exclusions fThis provided scope does not include the following items. If any of these
survey items are required by client please notify RSI and we will make the necessary scope and
cost revisions.) This survey does not include:
a. Boundary survey.
b. Preparation of new legal description and sketch for easements, encumbrances, or deed revisions_
o Interior fences, ponds,. buildings or other improvements_
d. Tilfe policy review and mappmg
e Any additional survey work will be based on an hourly rate or negotiated under a separate agreement
The Budget Cost of this project if agreed upon will be S8,000 00
See our attached I-fourly Rates Chart
We are pleased to supply you with this quote and look forward to working with you to complete this project_ To
accept this proposal. please read, sign and return If you have any questions or need additional information
about this proposal and or contract please call
Sincerely.
Larry P. Bowen. President Approved by
RAPID SURVEYING, [NC. Date
- 1 -
xiooKTRAcTstoiernonimog Ctermceil CcnllruMg Cortact_13130NTO No 03 Rapid Stave)ing_a1€S- Cterrmnl CUP- AECOM_dcc
City of Clermont
e mo
To: Wayne Saunders, City Manager
From: Tamara Richardson, PE, City Engineer'
CC:
Date: Apnl 4, 2011
Re: Consumptive Use Permit Renewal
Amendment 5 to Task Authorization No 11
AECOM
In February 2005, the City of Clermont Council authorized AECOM (successor in interest to
Boyle Engineenng) to perform engineering services to renew the City's Consumptive Use
Permit (CUP) with the St Johns River Water Management Distnct The onginal scope of
services for $79,196 00 was to respond to two Requests for Additional Information (RAI)
However, since CUP permitting has become such and involved and cumbersome process,
RAI No 1 took approximately one full year to respond to the District due to the complexity of
the questions and the necessary coordination with the Distnct's consultants
Our approach to the CUP Scope is to amend it as needed based on the District's response
and questions to our information, since it is impossible to predict the level of effort obtaining
the permit will require We are prepanng to respond to Request for Additional Information No
6 which includes wetland evaluation for all wetlands within the 01 foot drawdown contour
(approximately 400)
Amendment Nos 1, 2, 3 and 4 to Task Authorization No 11 provided a total additional
$127,089 00
I recommend approval of the additional fees of $52,850 00 for AECOM to continue with the
Consumptive Use Permit renewal with the St. Johns River Water Management Distnct
1