Loading...
2012-10 lin't TETRA TECH March 14, 2012 Mrs. Tamara Richardson, P.E. City of Clermont 685 West Montrose Street, 2nd Floor Clermont, Florida 34711 Subject: East Side WRF Reclaimed Water Storage Tank Tt # 200 -BP Clermont/Eastside WRF Dear Mrs. Richardson: Tetra Tech is pleased to furnish this proposal for professional engineering services to assist the City of Clermont with design, permitting, bidding and construction services for the proposed project referenced above. A detailed scope of services, compensation summary, and project schedule are attached hereto. Tetra Tech looks forward to providing these services to the City of Clermont. If you should have any questions, please do not hesitate to contact me at 407 - 839 -3955. Very truly yours, APPROVED: Tetra Te h City of Clermont D. Fox, P.E. B ' y = t = 4 Aim Vice President Date: ,Ei / 3 Attachments G:\Administrative1WORDPROC\BP Proposals \General \Clermont \Eastside WTP\Richardson 031412.doc C: Lauren R. Springer, P.E., Tetra Tech Sally Alfieri, Tetra Tech 201 East Pine Street. Suite 1000. Orlando, FL 32801 Tel 407.839.3955 Fax 407.839.3790 www.tetratech.com r EXHIBIT "A" CITY Of CLERMONT EAST SIDE WATER RECLAMATION FACILITY RECLAIMED WATER GROUND STORAGE TANK SCOPE OF SERVICES I. PROJECT DESCIPTION The City of Clermont (City) owns and operates the East Side Water Reclamation Facility (WRF) located at 3335 Hancock Road, Clermont, Florida. The WRF includes storage and high service pumping for distribution of reclaimed water. To support expansion of the reclaimed water system, the City proposes to construct a 3.0 million gallon (MG) reclaimed water ground storage tank on the WRF site adjacent to the existing tank. Specific details regarding the contemplated facilities and services are presented below: 1. Construction of a new 3.0 MG prestressed concrete ground storage tank, site work, yard piping, and miscellaneous instrumentation. Tetra Tech will provide engineering services to assist the City with design, permitting bidding and construction administration services of the proposed ground storage tank project. II. SCOPE OF SERVICES A. Design Design will result in preparation of the bidding and contract documents, engineering drawings and technical specifications, which will be submitted to the City for review at 90- and 100 - percent completion levels. The 90- percent submittal will include: plan, section and required details of the ground storage tank, site work, yard piping, and miscellaneous electrical/instrumentation drawings, project specifications (bidding and technical), and opinion of project cost. The 100 - percent submittal will include: updated engineering drawings and specifications (technical and bidding) incorporating the comments received from the City on the 90- percent submittal, and an updated opinion of project cost. Three (3) sets of drawings and specifications will be provided to the City for each review. A review meeting will be held with the City following the 90- percent submission. To ensure proper design of the facilities, Tetra Tech will obtain approval from the City for any substantial changes in the preliminary design prior to incorporation in the final design. Tasks to be completed during this phase are summarized below: 1. Prepare a comprehensive project manual that contains bidding and contractual documents (Divisions 0 and 1) and technical specifications for competitive JDF /sma/Eastside WRF /Scope Clermont Tank Tt# BP Clermont -1- 121411 bidding (Divisions 2 through 16). The project manual and its contents will be formatted in accordance with the Construction Specifications Institute (CSI). 2. A preliminary list of drawings is presented below: General Cover Sheet, Location Map, General Notes, and Drawing Index Legend and Abbreviations Civil Existing Conditions & Erosion Control Plan Grading & Geometry Plan Mechanical/Instrumentation Ground Storage Tank & Yard Piping — Plan and Sections Ground Storage Tank — Details B. Permitting Tetra Tech will prepare and submit the following permit applications and supporting documentation to the Florida Department of Environmental Protection (FDEP) and the City of Clermont Planning and Zoning Department as required to obtain permits for construction and operation of the proposed facilities. Tetra Tech will also respond to requests for additional information (RAIs) from permitting agencies to clarify the original applications. All permit application fees will be paid by the City. 1. Prepare and submit FDEP Permit Application for a Minor Revision to a Wastewater Facility or Activity Permit, Form 62- 620.910(9). 2. Prepare and submit an application for a FDEP Environmental Resource Permit (ERP) Modification. 3. Prepare and submit an application for site development review to the City's Planning and Zoning (P &Z) Department. Attend one (1) meeting with the City's P &Z Staff. Respond to the P &Z's comments and resubmit final documents for approval. C. Bidding Upon advertisement of the project by the City, Tetra Tech will assist the City with bidding of the project and shall complete the following tasks: 1. Provide one (1) copy of the Contract Documents (engineering drawings and specifications) in PDF format for distribution to potential bidders by the City's Purchasing Department. JDF /sma/Eastside WRF /Scope Clermont Tank Tt# BP Clermont -2- 121411 2. Prepare for and administer one (1) pre -bid conference. 3. Respond to questions and prepare addenda as required to interpret, clarify or expand the bidding documents. The City Purchasing Department will distribute all addenda. 4. Review and evaluate the apparent low bidder's qualifications for undertaking the work and make recommendation of the award of the contract. 5. Prepare two (2) copies of a conformed set of Contract Documents for the City and one (1) reproducible set for the recommended Contractor. D. Construction Administration Upon award of the project, Tetra Tech will assist the City with construction administration and shall complete the following tasks based on a construction duration of 9- months: 1. Prepare for and administer one (1) preconstruction meeting. 2. Attend periodic progress and specially scheduled meetings throughout progress of work. Progress meetings will be held as needed to coordinate work in progress. It is anticipated that 6- meetings will be needed at an average duration of two (2) hours each, followed by a site visit at an average duration of one (1) hour each, based on an anticipated construction duration of 9- months. 3. Make visits to the site at intervals appropriate to the various stages of construction in order to observe the progress and quality of the Work. It is anticipated that one (1) site visit in addition to Item No. D.2 above with an average visit duration of approximately three (3) hours will be required, based on an anticipated construction duration of 9- months. 4. Review shop drawings to determine conformance with the design concepts of the project and compliance with the requirements provided in the contract documents. 5. Review requests for information (RFIs), provide interpretation of construction documents, and issue written clarifications or interpretations. 6. Review the Contractor's Application for Payment and the accompanying data and schedules, determine the amounts owed to the Contractor, and advise the City of the recommended payments to the Contractor. 7. Upon written request by the Contractor, conduct a substantial completion inspection of the project with the City and distribute a punch list of observed deficiencies to be completed by the Contractor prior to the final completion date. The project will be certified substantially complete only if the work is sufficiently JDF /sma/Eastside WRF /Scope Clermont Tank Tt# BP Clermont -3- 121411 complete in accordance with the contract documents, so that the work can be utilized for the purposes for which it is intended. Final completion inspection to verify that the punch list items have been addressed will be performed by the City. 8. Review the Contractor's as-built submittals monthly for adequacy and review listing of deviations from the construction permit and approved construction documents. Prepare record drawings for City's use from information provided by the Contractor delineating the dimensions, location, and elevation of all facilities constructed. Provide the City with one (1) CD -ROM electronic file of record drawings in PDF format and three (3) sets of prints of the record drawings. 9. Prepare and submit certifications and required supporting documentation to regulatory agencies having jurisdiction. E. Survey and Geotechnical 1. During design, Tetra Tech shall provide a topographic survey of the project site (area adjacent to existing storage tank). Establish horizontal and vertical control based on Lake County datum NAD83 (2007) Florida East Zone, NAVD 1988. 2. During design, Tetra Tech shall arrange and pay for an independent soils investigation/testing firm to provide necessary soils data and other pertinent information required for design of the following. Soil borings logs and classifications, existing groundwater levels and estimated seasons high levels, structural foundation requirements, and pipe trench preparation and backfill requirements will be submitted in report format. a. For design of the proposed structural element of the WTP, it is estimated that the investigation will include one (1) SPT boring to a depth of 100 feet, and three (3) CPT borings to a depth of 50 feet. III. COMPENSATION SUMMARY The total lump sum compensation for the Scope of Services described in Section II is $58,540. Attachment B presents a detailed breakdown of the estimated compensation for the Scope of Services. 1. Design $21,270 2. Permitting 6,610 3. Bidding 4,005 4. Construction Administration 15,305 5. Geotechnical 10,600 6. Direct Costs 750 TOTAL $58,540 JDF /sma/Eastside WRF /Scope Clermont Tank Tt# BP Clermont -4- 121411 IV. SCHEDULE The anticipated delivery schedule for the project is presented below: Cumulative Days Milestone Task Duration in Days After Notice to Proceed Notice to Proceed 0 0 90% Design Submittal, Survey 45 45 Geotechnical, Permitting Submission City 90% Design Review & Meeting 10 40 100% Submittal 10 65 Receive Permits 35 100 JDF /sma/Eastside WRF /Scope Clermont Tank Tt# BP Clermont -5- 121411 A ''', N m p o R R ,4 3 `o 3 R± a y� °$ m N d F 8�g � '� n o 0 '�U C H e .. c p n . 7 i .. m . J n n '^ v ~ N W d N N .. N tv U a` m 0 O Q o 0 °'- ^ N ul at 1 ;:: O N ~ O N I � 1 111111 11111111 ia8aninS 1111111111111111 1111111111111 "" 11111 c',00 Walo, 7 W _ Z,au8'ZA:> ° 1 111111 Il fU o, Al 4 111111 1111111.1111 linianal plaau 8u3 11 111 1 1111111 ._ 11 1111 � Iil'+�ulsu3 J'HIIHI I ill 111 II I i 14 ("1"1 iir 111111 1111 11111 . N A - i C M 1— CD OD M L 8 L at f+ f0 a o f0 2 s 2 i yam- 4 s O LL E E S Ti 03 Q e g v L 13 E L ° a Qs 2 ` V all L 1 v 0 . . 11! c t z _N g g O N el hh Fi 1 a v a -6E .g e 6 c 88 uOm pss 5 gEQ g '3¢ � . ../ , C s Y G. i S Y I i d CU E a a 2 m s f 1 i 1- City of Clermont e mo To: Wayne Saunders, City Manager From: Tamara Richardson, PE, City Engineer CC: Date: February 9, 2012 Re: Tetratech Scope of Services 3 MG Reclaimed Water Storage Tank The St. Johns River Water Management District offered $10 million in funding assistance for alternative water supply projects with an emphasis on MFL mitigation. In response, staff requested a scope of services from Tetratech to design, permit and provide construction services for a 3 million gallon reclaimed water storage tank to be constructed at the EWRF and requesting funding assistance (approximately 40 percent) from the District for construction. Since the District is giving preference to "shovel ready" projects, it is imperative that we get the tank designed and ready for bid as soon as possible. The attached task order authorizes the engineer to design, permit and provide construction services for the construction of the 3 MG Reclaimed Water Storage Tank Project. The scope of services is for $58,540.00. Since the project was not included in the current fiscal year budget, a budget amendment would be required. Staff is requesting authorization for Tetratech to perform professional engineering services to design, permit and provide construction phase services for construction of a new 3 MG reclaimed water storage tank for $58,540.00. 1