2012-71 CONSTRUCTION CONTRACT CHANGE Change No One(1) Date: 09/28/12 Project Clermont Community Center NE Job No: 1001.00 Architect/Engineer CT Hsu&Aseodatea To(Contractor): Mark Construction Company 471 Gold Medal Ct. Longwood,FL 32750 Your Proposal has been accepted for making the following changes: DESCRIPTION OF ADJUSTMEP DECREASE CREASE Reconciliation of Approved CORe to Date COR#1-RFI#4 Approved Value Engineering $ 8,450.00 COR#3-RFI#12 Discover/Investigation of Slab Debris $ 2,115.00 COR#4-RFI#12 T&M Removal of Slab Debris $ 8,587.00 COR#5-RFI#13 T&M Removal of Parking Lot Debris $ 4,090.00 COR#7R2-PR#2R2 Streetecape Modifications $ 60,073.00 COR#18-OPO#1 Thru 8117/12(Tax Savings of$28,580.13 to date) $ 494,915.57 $ 501,366.67 $ 62,785.00 NOTICE TO PROCEED DATE: 5/14/2012 ORIGINAL CONTRACT SUM: $3,113,600.00 Contract Time -Days Complete' Total $ 601,385.67 $ 62,785.00 Present Contract 300 3/10/2013 Net New $ (438,800.57) TMs Adjustment 7 Calendar Days , Present Contract Sum _ _ , $ _ 3.113,500.00 New Conl act Time 307 13 ew Contract gum 2,674,899.4433 This Change Order Is an amendment-to the Owner-Contractor Agreement, and all contract provisions shall apply unless specifically exempted. The amount and time Change designated are the maximum agreed to by both the Owner and the Contractor for this change.in consideration of the foregoing adjustments In Contract Time and Contract Sum, the Contractor hereby releases Owner from all Claims, demands, or causes of action arising out of the transactions, eve • and occurrences giving rise to this Change Order. This written Change Order Is the entire agreement b- Owner and Contractor with respect to this Change Order.No other agreement or modification shall apply to this • ct amendment unless expressly provided herein. AGREED • /b '_ /2- ONTRACTOR DATE • //77 09/28/2012 ARCHITECTI - ER DATE 0- CI PA 11.-;1 " LERMONT 'BAT