2012-74 CONSTRUCTION CONTRACT CHANGE
41.111410 coRrounow
Change No.: One(1) Date: 10/16/12
Project: Clermont Community Center NE Job No.: 1001.00
Architect/Engineer CT Hsu&Associates CM Job No.: 201141
To(Contractor): Ajax Building Corporation
109 Commerce Blvd.
Oldsmar, FL 34677
Your Proposal has been accepted for making the following changes:
DESCRIPTION OF ADJUSTMENT DECREASE INCREASE
Contract Extension to End of Project(see attached email dated 8/29/12)
5 Additional Months at$8,300/mth(thru 3/6/13) $ 41,500.00
$ - $ 41,500.00
START OF CM SERVICES: 12/7/2011
ORIGINAL CONTRACT SUM: $83,000.00
Contract Time Days Complete* Total $ - $ 41,500.00
Present Contract 304 10/6/2012 Net New $ 41,500.00
This Adjustment 151 Calendar Days Present Contract Sum $ 83,000.00
New Contract Time 455 3/6/2013 New Contract Sum $ 124,500.00
This Change Order is an amendment to the Owner-Contractor Agreement, and all contract provisions shall apply unless
specifically exempted. The amount and time Change designated are the maximum agreed to by both the Owner and the
Contractor for this change. In consideration of the foregoing adjustments in Contract Time and Contract Sum, the Contractor
hereby releases Owner from all Claims, demands, or causes of action arising out of the transactions, events and
occurrences givi . rise to this Change Order. This written Change Order is the entire agreement between Owner and
Contractor wi -spect to this Change Order. No other agreement or modification shall apply to this contract amendment
unless expr-- ly pr'vided herein.