2013-91 f Sti
CONSTRUCTION CONTRACT CHANGE
Change No: Three(3) Date. 02/28/13
Protect Clermont Community Center NE Job No 1001.00
Architect/Engineer CT Hsu&Associates
To(Contractor): Mark Construction Company
471 Gold Medal Ct.
Longwood,FL 32750
Your Proposal has been accepted for making the following changes:(excludes un-reviewed time adjustments for the below)
DESCRIPTION OF ADJUSTMENT -DECREASE INCREASE
Reconciliation of Approved CORE to Date
COR#2R RFI#8 Tree Removal Final Adjustment $ 1,485.00
COR#SArev.ASt#1R Revised Conformance Drawings $ 16,926.00
COR#14 PR#4 ASI#5 Toilet Accessory Modifications $ 1,140.00
COR#22 RFI#39 FEC Modifications $ 388.00
COR#24 PR#7 Power and Cable to Two T.V's $ 764.00
COR#25 PR#8 Drywall Changes per A6.201 $ 97.00
COR#26 Credit for Missing Brick Face on Tilt Panel#2 $ 2,000.00
COR#27 PR#9 Credit for Knox Box $ 497.00
COR#28 RFI#55 P19 Door Opening Modification $ 1,743.00
COR#29 Removal of Fire Une Valve $ 1,545.00
COR#30 Added Veranda Sprinkler Heed $ 812.00
COR#31 Storm 8'to 12"HDPE Connection $ 1,243.00
COR#33 PR#12 Grading at NW Corner of Bldg to Dumpster $ - $ -
COR#34 RFI#62 Change Power Supply to Well Pump $ 2,205.00
COR#36 Added Surveying for Alignment of Desoto $ 1,472.00
COR#37 ASI#1 Door Modifications prior to ASI#1 R $ 3,531 00
COR#38 ASI#11 R2 Storefront Door Modifications $ 4,069.00
COR#39 A$I#12 Kitchen Hood Insulation $ 658.00
COR#40 ASI#13 New Grades at South Plaza $ - $ -
COR#41 RFI#68 Storm Conflict with Existing Electrical Pole $ 1,860.00
COR#42 Modify Tactile Warning North Side of Bldg Entrance $ 260.00
• COR#43 ASI#15 Desoto/ Lake Intersection Revisions $ 3,890.46
' COR#44 Replace Drives not shown on Plans $ 3,367.00
COR#45 PR14R2 TV Recptide and deleted Projection Screen In Board Rm. $ 135.00
_ COR#48 PR#15 Electric in Sound Closet _ $ 799.00
COR#47 PR#16 Addressable Shunt Tnp Relay for Fire Alarm System $ 3.731.00
COR#48 Credit for Off-Site Conduit $ 3,614.00
COR#49 Credit for Installation of Three Light Poles $ 885.00
COR#53 PR#18R2 Lake/Minneola Intersection Modifications $ 16,81000
COR#54 PR#19 Credit for Key Cores $ 610.00
COR#55 PR#20 Credit for Relnspection Costs $ 1,468.00
COR#57 ODP Adjustment#2 - 354,50617
$ 363,812.17 $ 68,678.46
NOTICE TO PROCEED DATE: . 5/14/2012
ORIGINAL CONTRACT SUM: $3,113,500.00
Contract Time Days - Complete' Total _ $ 363,812.17 $ 68,678.48
Present Contract 307 - 3/17/2013 Net New $ (295,133.71)
This Adjustment 0 Calendar Days Present Contract Sum $ 2,674,899.43
New Contract Time 307 3/17/2013 New Contract Sum $ 2,379,765.72
This Change Order Is an amendment to the Owner-Contractor Agreement, and all contract provisions shall apply
unless specifically exempted. The amount and time Change designated are the maximum agreed to by both the
Owner and the Contractor for this change. In consideration of the foregoing adjustments In Contract The and Contract
Sum, the Contractor hereby releases Owner from all Claims, demands, or causes of action arising out of the
transactions, events and occurrences giving rise to this Change Order. This written Change Order is the entire
agreement between Owner and Contractor with respect to this Change Order.No other agreement or modification shall
apply to this contract amendment unless expressly provided herein.
AGREED
CONTRACTOR DATE
AR - : _ ER DA-MTh
• _25:445
CI OF CLERMONT _DATE
1
J' ` . ,
I 1'"...
421 Gold Medal Court*Longwood,Florida 32760
Phone:-407.831.6275•Fax: 407.332.5311
Change Order Request No.#8A Revised
Jenkins Community Center
Date.9/20/2012 Revised 11/26/12 2nd Revision 1/18/13
To Ajax Building Corporation
From Mark Construction
Description of Work.
ASI#1 R Conformance Drawings
DESCRIPTION QUANT UNIT SUB SUBCONT MATRUTATERIAL LABR LABOR TOTAL
U P UP U.P. ,
4Evolution Inc (See attached quote) 1 LS 8530 $ 8,530 0 $ - 0 $ - $ 8,530
Adjustment to LV Solutions Ind fee See Email -1 LS 660 $ (660) 0 $ - 0 $ - $ (660)
Schwenn Mech(see attached quote) 1 LS 4989 $ 4,989 0 $ - 0 $ - $ 4,989
Provide T V Video of Sanitary Line 1 LS void void 0 $ - 0 $ - void
Will not be required per request of CTHSU
Magruder(see attached quote) 1 LS 1574 $ 1,574 0 $ - 0 $ - $ 1,574
Plan Re.roductlon 20 SETS 0 $ - 35 $ 700 0 $ - $ 700
SUB-TOTALS $ 14,433 $ 700 $ - $ 15,133
'SALES TAXES 7 PERCENT $ 49 8 49
LABOR BURDEN 42 PERCENT $ - $ -
SUB-TOTAL $ 15,182
BUILDERS RISK $ 23
PERFORMANCE BOND $ 182
SUB-TOTAL $ 15,387
O.H &PROFIT- 10 PERCENT $ 1,539
TOTAL CHANGE ORDER NUMBER 8A 2nd Revision- $ 16,926
The additional work requires 0 days to be added to the contract time
, Acceptance of Change Order -
Our signature below represents our agreement to proceed with the desenbed work for the amount and durations as listed above
Mark Construction Co.
Ron Bryan,Project Manager
Your signature below authorizes Mark Construction Co to proceed with the above additional work,the additional days and dollar amounts listed above
will be added to the contract
Owner or Owner's Rep.
Signature,Date
Rejection of Change Order i Architect
rep name and title
Reason for Rejection: Signature,Date Printed Name&Title
f e
TULAIIIC
421 Gold Medal Court'Longwood,Florida 32760
Phone. 407 831 6275•Fax: 407 332 5311
Change Order Request No.#22
Jenkins Community Center
Date 9/18/2012
To Ajax Building Corporation
From Mark Construction
Description of Work RFI#39R
Revise FE Cabinets from a full depth cabinet to a semi-recessed cabinet.
DESCRIPTION QUANT UNIT SUB. SUBCONT MATRVIATERIALLABR LABOR TOTAL
U P U.P U P
Smith&Wassatt(see attached quote and cut sht) 1 LS 348 $ 348 0 $ - 0 $ - $ 348
1 LS 0 $ - 0 $ - 0 $ - $ -
SUB-TOTALS $ 348 $ - $ - $ 348
SALES TAXES 7 PERCENT $ - $ -
LABOR BURDEN 42 PERCENT $ - $ -
SUB-TOTAL
$ 348
BUILDERS RISK $ 1
PERFORMANCE BOND $ 4
SUB TOTAL $ 353
0 H &PROFIT 10 PERCENT $ 35
TOTAL CHANGE ORDER NUMBER 22 $ 388
The additional work requires 0 days to be added to the contract time
Acceptance of Change Order
Our signature below represents our agreement to proceed with the described work for the amount and durations as listed above
Mark Construction Co.
Ron Bryan,Project Manager
Your signature below authorizes Mark Construction Co to proceed with the above additional work,the additional days and dollar amounts listed above
will be added to the contract
Owner or Owner's Rep.
Signature,Date
Rejection of Change Order I Architect
rep name and title
Reason for Rejection: Signature,Date Printed Name 8 Title
i
r ,
IVL.A
.141(
c.v... 1\T
+sor4rn,>,rx�r.
421 Gold Medal Court•Longwood,Florida 32760
Phone. 407,831.6275'Fax. 407.332.5311
Change Order Request No.#2R
Jenkins Community Center
Date 6/22/2012 Revised 8/15/12
To Ajax Building Corporation
From.Mark Construction
Descnption of Work
RFI#8 Removal of Oak Tree at Lake Ave Entrance to New Parking Area
Price adjustment for additional trees to be saved and additional trees to be removed
DESCRIPTION QUANT UNIT SUB SUBCONT MATRVIATERIAI LABR LABOR TOTAL
U.P U P U P
Fohsee Construction:Tree Removal Pricing 1 LS 1314 $ 1,314 0 $ - 0 $ - $ 1,314
(see attached quote)
8Y9i1—$--47Bi?8 5_ 0 $ $ 9,828
'' — 'Six pine trees were removed by the City of
The remainder of the tree adjustment survey included 4 trees to be s C'y On.ditionzi"tr c to x rcmord,which-- -
tured out to be a wash.
SUB-TOTALS $ .142 $ - $ - $ 60.42
SALES TAXES 7 PERCENT $ - $
LABOR BURDEN 42 PERCENT $ - $ -
SUB-TOTAL
BUILDERS RISK Sub-total $ 1,314 $ B
PERFORMANCE BOND S.Risk $ 2 $ >o).
O H &PROFIT 10 PERCENT Per(. Bnd $ 16 ; $
I TOTAL CHANGE ORDER NUMBER TWO REVISED $ %e 3 I
The additional work requires 0 days to be added to the contract time
s21;ad ,,,L.jalial
Acceptance of Change Order }}�� Q
Our signature below represents our agreement to proceed with the described work for the amount and durat ed above.1,4655
ohs¢d1 kt
Mark Construction Co. , APPROVED �1
Ron Bryan,Project Manager i
By rbryan at 4:09 pm, Nov 26, 2012 f
Your signature below authorizes Mark Construction Co to proceed with the above additional work,the additional days end dollar amounts listed above
will be added to the contract
Owner or Owners Rep.
Signature,Date
Rejection of Change Order I Architect
rep name and title
Reason for Rejection' Signature,Date Printed Name&Title
i
lliCARK
421 Gold Medal Court•Longwood,Florida 32760
Phone. 407.831.8275•Fax 407.332 5311
Change Order Request No.#14
Jenkins Community Center
Date'9/17/2012
To Ajax Building Corporation
From Mark Construction
Description of Work P R #4
Toilet Accessory Modifications_
DESCRIPTION QUANT UNIT SUB SUBCONT MATR 1ATERIAL LABR LABOR TOTAL
U P. U.P U P
Smith&Wassatt. See Attached Quote 1 LS 1023 $ 1,023 0 $ - 0 $ - $ 1,023
1 LS 0 $ - 0 $ - 0 $ - $
SUB-TOTALS $ 1,023 $ - $ - $ 1,023
SALES TAXES 7 PERCENT $ - $ -
LABOR BURDEN 42 PERCENT $ - $ -
SUB-TOTAL $ 1,023
BUILDERS RISK $ 2
PERFORMANCE BOND $ 12
SUB-TOTAL $ 1,037
O H. &PROFIT 10 PERCENT $ 104
TOTAL CHANGE ORDER NUMBER 14 $ 1,140 I
The additional work requires 0 days to be added to the contract time
Acceptance of Change Order
Our signature below represents our agreement to proceed with the described work for the amount and durations as listed above
Mark Construction Co.
Ron Bryan,Project Manager
Your signature below authorizes Mark Construction Co to proceed with the above additional work,the additional days and dollar amounts listed above
will be added to the contract
Owner or Owner's Rep.
Signature,Data
Rejection of Change Order I Architect
Reason for Rejection' rep name and title
1 Signature,Date Printed Name&Title
AILMITROLICTION
nernawnewormul
421 Gold Medal Court•Longwood,Florida 32750
Phone: 407.831.6275•Fax: 407.332.5311
Change Order Request No.#22
Jenkins Community Center
Date.9/18/2012
To Ajax Building Corporation
From Mark Construction
Description of Work RF1#39R
Revise FE Cabinets from a full depth cabinet to a semi-recessed cabinet
DESCRIPTION QUANT UNIT SUB SUBCONT MATRMATERIAL LABR LABOR TOTAL
U P. U.P U.P
Smith&Wassatt(see attached quote and cut sht) 1 LS 348 $ 348 0 $ - 0 $ - $ 348
1 LS 0 $ - 0 $ - 0 $ - $ -
SUB-TOTALS $ 348 $ - $ - $ 348
SALES TAXES 7 PERCENT $ - $ -
LABOR BURDEN 42 PERCENT $ - $ -
SUB-TOTAL $ 348
BUILDERS RISK $ 1
PERFORMANCE BOND $ 4
SUB-TOTAL $ 353
O H &PROFIT 10 PERCENT $ 35
(TOTAL CHANGE ORDER NUMBER 22 $ 388'
The additional work requires 0 days to be added to the contract time
Acceptance of Change Order
Our signature below represents our agreement to proceed with the described work for the amount and durations as listed above
Mark Construction Co.
Ron Bryan,Project Manager
Your signature below authorizes Mark Construction Co to proceed with the above additional work,the additional days and dollar amounts listed above
will be added to the contract
Owner or Owner's Rep.
Signature,Date
Rejection of Change Order I Architect
rep name and title
Reason for Rejection. Signature,Date Printed Name&Title
K
aay .r�AlLarrILUCTIONT
v,
421 Gold Medal Court•Longwood,Florida 32750
Phone: 407.831.6275•Fax. 407 332.5311
Change Order Request No.#24
Jenkins Community Center
Date 10/30/12-
To Ajax Building Corporation
From Mark Construction
Description of Work.Proposal Request*7
Provide electric power and coax cabling for two(2)TVs
DESCRIPTION QUANT UNIT SUB SUBCONT MATRVIATERIAL LABR LABOR TOTAL
UP UP UP
4Evolution Coaxial and Electric(see attached) 1 LS 595 $ 595 0 $ - 0 $ - $ 595
Backing for Two TV Mounts 2 EA 45 $ 90 0 $ - 0 $ - $ 90
0 0 $ - 0 $ - 0 $ - $ -
SUB-TOTALS $ 685 $ - $ - $ 685
SALES TAXES 7 PERCENT $ - $ -
LABOR BURDEN 42 PERCENT $ - $ -
SUB-TOTAL
BUILDERS RISK $ 685
$ 1
PERFORMANCE BOND $ 8
SUB-TOTAL $ 694
O.H &PROFIT 10 PERCENT $ 69
TOTAL CHANGE ORDER NUMBER 24 $ 764 I
The additional work requires 0 days to be added to the contract time
Acceptance of Change Order
Our signature below represents our agreement to proceed with the described work for the amount and durations as listed above
Mark Construction Co
Ron Bryan,Project Manager
Your signature below authorizes Mark Construction Co to proceed with the above additional work,the additional days and dollar amounts listed above
will be added to the contract
Owner or Owners Rep.
Signature,Date
Rejection of Change Order 'Architect
rep name and title
Reason for Rejection: Signature,Data Printed Name&Title
1 ,
TOILggilICITOTIT
twetrektmgwwwe..we.
421 Gold Medal Court•Longwood,Florida 32750
Phone: 407.831.6275•Fax: 407.332.6311
Change Order Request No.#25
Jenkins Community Center
Date 11/26/12
To Ajax Budding Corporation
From Mark Construction
Description of Work
PR#7 Drywall Modifications
DESCRIPTION QUANT UNIT SUB. SUBCONT MATRVIATERIAL LABR LABOR TOTAL
U.P. U P U.P
Baylor Plastering Credit for 240 SF of drywall 1 LS -96 $ (96) 0 $ - 0 $ - $ (96)
and trim to build out areas in the wall
1 SF 0 $ - 0 $ - 0 $ - $ -
1 LS 0 $ - 0 $ - 0 $ - $ -
SUB-TOTALS $ (96) $ - $ - $ (96)
SALES TAXES 7 PERCENT $ - $ -
LABOR BURDEN 42 PERCENT $ - $
SUB-TOTAL
$ (96)
BUILDERS RISK $ (0)
PERFORMANCE BOND $ (1)
SUB-TOTAL
$ (97)
TOTAL CHANGE ORDER NUMBER 25 $ (97)1
The additional work requires 0 days to be added to the contract time
Acceptance of Change Order
Our signature beiow represents our agreement to proceed with the described work for the amount and durations as listed above
Mark Construction Co
Ron Bryan,Project Manager
Your signature below authorizes Mark Construction Co to proceed with the above additional work,the additional days and dollar amounts listed above
will be added to the contract
Owner or Owners Rep
Signature,Date
Rejection of Change Order 1 Architect
rep name and title
Reason for Rejection. Signature,Date Printed Name 8 Title
,
AlLitaresTIETICTECON
PAM Irvi■me
421 Gold Medal Court•Longwood,Florida 32750
Phone. 407.831.6275'Fax: 407.332.5311
Change Order Request No.#26
Jenkins Community Center
Date 10/30/2012
To Ajax Building Corporation
From Mark Construction
Description of Work:
Deletion of Bnck Veneer from Panel No 2 Panel will be painted with a accent color as selected by the architect
DESCRIPTION QUANT UNIT SUB SUBCONT MATRVIATERIAL LABR LABOR TOTAL
UP. UP UP.
Credit for veneer on panle#2 1 LS -2000 $ (2,000) 0 $ - 0 $ - $ (2,000)
1 LS 0 $ - 0 $ - 0 $ - $
SUB-TOTALS $ (2,000) $ - $ - $ (2,000)
SALES TAXES 7 PERCENT $ - $
LABOR BURDEN 42 PERCENT $ - $ -
II TOTAL CHANGE ORDER NUMBER 26 $ (2,000)1
The additional work requires 0 days to be added to the contract time
Acceptance of Change Order
Our signature below represents our agreement to proceed with the described work for the amount and durations as I,sted above
Mark Construction Co.
Ron Bryan,Project Manager
Your signature below authorizes Mark Construction Co to proceed with the above additional work,the additional days and dollar amounts listed above
will be added to the contract
Owner or Owner's Rep.
Signature,Date
Rejection of Change Order 'Architect
rep name and title
Reason for Rejection: Signature,Date Printed Name 8 Title
NIUSILITCTICONI,
421 Gold Medal Court•Longwood,Florida 32750
Phone: 407.831.6275*Fax: 407.332.5311
Change Order Request No.#27
Jenkins Community Center
Date 10/30/12
To. Ajax Building Corporation
From Mark Construction
Description of Work.Proposal Request No 9
Credit to delete Knox Box called for in Spec Section 10100
DESCRIPTION QUANT UNIT SUB SUBCONT MATR 1ATERIAL LABR LABOR TOTAL
U.P. U P U P.
Deduct 4400 Senes,surf mt,w/tamper switch -1 EA 0 $ - 418 $ (418) 35 $ (35) $ (453)
1 LS 0 $ - 0 $ - 0 $ - $
■
SUB-TOTALS $ - $ (418) $ (35) $ (453)
SALES TAXES 7 PERCENT $ (29) $ (29)
LABOR BURDEN 42 PERCENT $ (15) $ (15)
I TOTAL CHANGE ORDER NUMBER 27 $ (4974
The additional work requires 0 days to be added to the contract time
Acceptance of Change Order
Our signature below represents our agreement to proceed with the deacnbed work for the amount and durations as listed above
Mark Construction Co.
Ron Bryan,Project Manager
Your signature below authorizes Mark Construction Co to proceed with the above additional work,the additional days and dollar amounts listed above
will be added to the contract
Owner or Owners Rep.
Signature,Data
Rejection of Change Order 'Architect
rep name and title
Reason for Rejection: Signature,Date Pnnted Name&T,tle
•
Ti/LAIM
WORN
421 Gold Medal Court'Longwood,Florida 32750
Phone: 407.831.6275'Fax 407.332.6311
Change Order Request No.#28
Jenkins Community Center
Date Oct 30,2012
To Ajax Building Corporation
From Mark Construction
Description of Work RFI#55
Required infill of concrete at P19 between foundation and SOG, panel layout did not take step down in foundation
into consideration
DESCRIPTION QUANT UNIT SUB. SUBCONT MATRVIATERIAI LABR LABOR TOTAL
UP UP UP
Magruder Concrete Will at P19 below SOG 1 LS 1563 $ 1,583 0 $ - 0 $ - $ 1,563
(see attached quote)
0 0 $ - 0 $ - 0 $ - $ -
SUB-TOTALS $ 1,563 $ - $ - $ 1,563
SALES TAXES 7 PERCENT $ - $
LABOR BURDEN 42 PERCENT $ - $ -
SUB-TOTAL $ 1,563
BUILDERS RISK $ 2
PERFORMANCE BOND $ 19
SUB-TOTAL $ 1,584
0 H &PROFIT 10 PERCENT $ 158
I TOTAL CHANGE ORDER NUMBER 28 $ 1,743 I
The additional work requires 0 days to be added to the contract time
Acceptance of Change Order
Our signature below represents our agreement to proceed with the described work for the amount and durations as listed above,
Mark Construction Co.
Ron Bryan,Project Manager
Your signature below authorizes Mark Construction Co to proceed with the above additional work,the additional days and dollar amounts listed above
will be added to the contract
Owner or Owners Rep
Signature,Date
Rejection of Change Order 'Architect
rep name and title
Reason for Rejection; Signature,Date Printed Name&Title
AILCYNAIIIIC
421 Gold Medal Court'Longwood,Florida 32750
Phone: 407.831.6276.Fax: 407.332.5311
Change Order Request No.#44
Jenkins Community Center
Date Dec.17,2012
To Ajax Building Corporation
From Mark Construction
Description of Work Additional dnveway demolition work on C-5,C-7 and C-8 not shown or Indicated on plan, the
addition of 5 drives not Indicated to be installed on C-5.(see attached drawings) and added sod not shown.
DESCRIPTION QUANT UNIT SUB SUBCONT MATRMATERIAL LABR LABOR TOTAL
U P. U P U.P.
Foshee•See Atached Quote
Removal of 3 drives on C-7 and 2 dnves on C-B 5 Ea 448-85-2----2149-6-- ---0—&—r--$---272-11—
(approx,1300 SF Oa$1 71 per SF)
Magurder See Attached Quote
Saw cut curb and exisltng pavement and remove
at 5 parking spaces on C-5) 1000 SF 1 95 $ 1,950 0 $ - 0 $1 w 780 I 1
(approx 1000 SF at$1 95 per S F) $ 2_,
Replace 5 parking spaces not shown on C-5 1000 SF 5 6 $ 5,600 0 $ - 0 $C 15, 0
(approx 1000 SF©$5 60 per S F) 1 SF 0 $ - 0 $ - 0 $ - $
1 SF 0 $ - 0 $ - 0 $ - $
Replace Bahia Sod 2800 SF 0 225 $ 630 0 $ 0 ( $
Replace st Augustine Sod 720 SF 0 315 $ 227 -9-
1 LS 0 $ - 0 $ - 0 $ - $
SUB-TOTALS $ 10,626 $ - $f F.3,020 626
SALES TAXES 7 PERCENT $ - L.- ,
LABOR BURDEN 42 PERCENT $— 3,020
sUB-TOTAL $ 5 10,:s`
BUILDERS RISK $ 36
PERFORMANCE BOND $ 3,061
SUB-TOTAL 10
O H &PROFIT 10 PERCENT $ 306 i
I TOTAL CHANGE ORDER NUMBER 44 $ 3,367
The additional work requires 0 days to be added to the contract time
Acceptance of Change Order
Our signature below represents our agreement to proceed with the described work for the amount and durations as listed above
Mark Construction Co.
Ron Bryan,Project Manager
Your signature below authorizes Mark Construction Co to proceed with the above additional work,the additional days and dollar amounts listed above
will be added to the contract
Owner or Owner's Rep
■
Signature,Date
Rejection of Change Order I Architect
rep name and tItle
Reason for Rejection. Signature,Date Pnnted Name&Title
ALARIC
VOieffritIqtrq
421 Gold Medal Court•Longwood,Florida 32750
Phone. 407 831.6275•Fax: 407.332.5311
Change Order Request No.#45
Jenkins Community Center
Date 1/21/2013
To Ajax Building Corporation
From.Mark Construction
Descnptian of Work Proposal Request 14-R2
Added Dedicated Receptacle and Data In BoardRm,Added Gand Box and Conduit for Future and Deleted Projection Screen
DESCRIPTION QUANT UNIT SUB SUBCONT MATRUTATERIAL LABR LABOR TOTAL
UP. UP UP
Provide Mouting Backing for future TV 1 EA 0 $ - 35 $ 35 70 $ 70 $ 105
4-Evolution Electncal and deletion of Pro) Screen 1 LS -272 $ (272) 0 $ - 0 $ - $ (272)
(See Atached Quote) 1 SF 0 $ - 0 $ - 0 $ - $ -
1 LS 0 $ - 0 $ - 0 $ - $ -
SUB-TOTALS $ (272) $ 35 $ 70 $ (187)
SALES TAXES 7 PERCENT $ 2 $ 2
LABOR BURDEN 42 PERCENT $ 29 $ 29
TOTAL CHANGE ORDER NUMBER 45 $ (135)1
The additional work requires 0 days to be added to the contract time
Acceptance of Change Order
Our signature below represents our agreement to proceed with the described work for the amount and durations as listed above
Mark Construction Co.
Ron Bryan,Project Manager
Your signature below authorizes Mark Construction Co to proceed with the above additional work the additional days and dollar amounts listed above
will be added to the contract
Owner or Owners Rep.
Signature,Date
Rejection of Change Order I Architect
rep name and title
Reason for Rejection: Signature,Date Printed Name&Title
AILAIRX
WtererarT e�
421 Gold Medal Court•Longwood,Florida 32750
Phone: 407.831 8275•Fax: 407.332.5311
Change Order Request No.#46
Jenkins Community Center
Date:2/4/2013
To Ajax Building Corporation
From Mark Construction
Description of Work Proposal Request#15
Electrical Power Supply to Storage Closet Room 110-D
DESCRIPTION QUANT UNIT SUB SUBCONT MATRVIATERIAL LABR LABOR TOTAL
U P U.P U P
4 Evolution One Quad Receptacle 1 LS 716 51 $ 717 0 $ - 0 $ - $ 717
1 L S 0 $ - 0 $ - 0 $ - $ -
SUB-TOTALS $ 717 $ - $ - $ 717
SALES TAXES 7 PERCENT $ - $ -
LABOR BURDEN 42 PERCENT $ - $ -
SUB-TOTAL $ 717
BUILDERS RISK $ 1
PERFORMANCE BOND $ 9
SUB-TOTAL $ 726
O H &PROFIT 10 PERCENT $ 73
I TOTAL CHANGE ORDER NUMBER 46 $ 799 I
The additional work requires 0 days to be added to the contract time
Acceptance of Change Order
Our signature below represents our agreement to proceed with the descnbed work for the amount and durations as listed above
Mark Construction Co.
Ron Bryan,Project Manager
Your signature below authonzes Mark Construction Co to proceed with the above additional work,the additional days and dollar amounts listed above
will be added to the contract
Owner or Owner's Rep
Signature,Date
Rejection of Change Order I Architect
rep name and title
Reason for Rejection. Signature,Date Printed Name&Title
•
M&RK
wri�
421 Gold Medal Court*Longwood,Florida 32750
Phone. 407.831.6275*Fax 407.332.6311
Change Order Request No.#47
Jenkins Community Center
Date 2/08/2012 Adjusted per#16R1 on 3 5 2013
To Ajax Building Corporation
From Mark Construction
Description of Work PR#16R1 revised 2122/13
Shunt Tripped receptacles
DESCRIPTION QUANT UNIT SUB SUBCONT MATRUATERIAL LABR LABOR TOTAL
U P. U.P U.P
4-Evolution First Receptacle shunt tripped 1 EA 2591 8 $ 2,592 0 $ - 0 $ - $ 2,592
Additional Receptacles 1 EA 755 02 $ 755 0 $ - 0 $ - $ 755
(will adjust per actual Receptacles installed) 1 LS 0 $ - 0 $ - 0 $ - $ -
SUB-TOTALS $ 3,347 $ - $ - $ 3,347
SALES TAXES 7 PERCENT $ - $ -
LABOR BURDEN 42 PERCENT $ - $ -
SUB-TOTAL $ 3,347
BUILDERS RISK $ 5
PERFORMANCE BOND $ 40
SUB-TOTAL
$ 3,392
O.H &PROFIT 10 PERCENT $ 339
I TOTAL CHANGE ORDER NUMBER 47 $ 3,731 I
The additional work requires'1'day to be added to the contract time.
Acceptance of Change Order
Our signature below represents our agreement to proceed with the described work for the amount and durations as lasted above
Mark Construction Co
Ron Bryan,Project Manager
Your signature below authorizes Mark Construction Co to proceed with the above additional work,the additional days and dollar amounts listed above
will be added to the contract
Owner or Owner's Rep.
Signature,Date
Rejection of Change Order I Architect
rep.name and title
Reason for Rejection: Signature,Date Printed Name 8 Title
M4RKaasenzNTNINm.om
421 Gold Medal Court•Longwood,Florida 32750
Phone: 407.831.6275•Fax: 407.332.5311
Change Order Request No.#40
Jenkins Community Center
Date•2/4/2013
To Ajax Building Corporation
From Mark Construction
Descnptlon of Work Credit for Electrical Conduit not required due to use of exisiting city owned conduit in place for future use
Credit Includes Conduit,labor for installation including removal cutting and patching
DESCRIPTION OUANT UNIT SUB SUBCONT MATRI1ATERIAL LABR LABOR TOTAL
UP UP UP.
4Evolution Credit Conduit Installation 980 L F -1 LS 2217 $ (2,217) 0 $ - 0 $ - $ (2,217)
Cut&Patch -980 LF 2 5 $ (2,450) 0 $ - 0 $ - $ (2,450)
Investigative Work.(discovery, 48 Hours 21 93 $ 1,053 0 $ - 0 $ - $ 1,053
( determine muting and clearing out lines) 0 0 $ - 0 $ - D $ - $ -
SUB-TOTALS $ (3,614) $ - $ - $ (3,614)
SALES TAXES 7 PERCENT $ - $ -
LABOR BURDEN 42 PERCENT $ - $ -
ITOTAL CHANGE ORDER NUMBER 48 $ (3,614)I
The additional work requires 0 days to be added to the contract time
Acceptance of Change Order
Our signature below represents our agreement to proceed with the described work for the amount and durations as listed above
Mark Construction Co.
Ron Bryan,Project Manager
Your signature below authorizes Mark Construction Co to proceed with the above additional work,the additional days and dollar amounts listed above
will be added to the contract
Owner orOwner'a Rep
Signature,Date
Rejection of Change Order I Architect
rip name and btle
Reason for Rejection: Signature,Date Printed Name&Title
M=4:01ARIC
rfarareve•. oms
421 Gold Medal Court•Longwood,Florida 32750
Phone: 407 8316275•Fax: 407 332.5311
Change Order Request No.#49
Jenkins Community Center
Date.02/04/2013
To Ajax Building Corporation
From:Mark Construction
Description of Work'
Credit for the Installation of Three Light Poles
Light Poles and Bases were turned over to the owner
DESCRIPTION QUANT UNIT SUB SUBCONT MATRMATERIAL LABR LABOR TOTAL
UP UP UP
4Evolutlon Credit for installation of three It poles -1 LS 885 $ (885) 0 $ - 0 $ - $ (885)
1 LS 0 $ - 0 $ - 0 $ - $ -
SUB-TOTALS $ (885) $ - $ - $ (885)
SALES TAXES 7 PERCENT $ - $ -
LABOR BURDEN 42 PERCENT $ - $ -
TOTAL CHANGE ORDER NUMBER 49 $ (885)
The additional work requires 0 days to be added to the contract time.
Acceptance of Change Order
Our signature below represents our agreement to proceed with the described work for the amount and durations as listed above
Mark Construction Co.
Ron Bryan,Project Manager
Your signature below authorizes Mark Construction Co to proceed with the above additional work,the additional days and dollar amounts listed above
will be added to the contract
Owner or Owner's Rep.
Signature.Date
Rejection of Change Order 'Architect
rep name and title
Reason for Rejection. Signature,Date Printed Name&Title
M4RK
T 16LV 0144 oMPA �rJ
421 Gold Medal Court•Longwood,Florida 32760
Phone: 407.831.6276*Fax: 407 332.6311
Change Order Request No.#53
Jenkins Community Center
Date:2/11/2013
To: Ajax Building Corporation
From:Mark Construction
Description of Work:Pr#18 R2
Cost to Saw-Cut and remove existing curb,base,and pavement and replace with new curb configuration.
Removal of Poured curb.Adjust Intersection elevations,added base pavement and sidewalks
DESCRIPTION QUANT UNIT SUB SUBCONT MATRVIATERIAIIABR LABOR TOTAL
U.P. U.P U.P.
Foshee Cnstructton(see attached quote) 1 LS 14047 $ 14,047 0 $ - 0 $ - $ 14,047
Added sidewalk 275 SF 3.75 $ 1,031 0 $ - 0 $ - $ 1,031
Added MOT totaling 3 weeks,2 with Foshee 1 WK 0 $ - 0 $ - 0 $ - $ -
Added Supervison MCC 3 WKS 0 $ - 0 $ - 0 $ - $ -
0 0 $ - 0 $ - 0 $ - $ -
SUB-TOTALS $ 15,078 $ - $ - $ 15,078
SALES TAXES 7 PERCENT $ - $ -
LABOR BURDEN 42 PERCENT $ - $ -
SUB-TOTAL $ 15,078
BUILDERS RISK $ 23
PERFORMANCE BOND $ 181
SUB TOTAL $ 15282
O.H. &PROFIT 10 PERCENT $ 1,528
TOTAL CHANGE ORDER NUMBER 63 $ 16,810
e ad. i•na wor requires ;%days o e a ed'to t e contract tme
Acceptance of Change Order
I
Our signature below represents our agreement to proceed with the described work for the amount end durations as listed above
1
Mark Construction Co
Ron Bryon,Project Manager
Your signature below authorizes Mark Construction Co to proceed with the above additional work,the additional days and dollar amounts listed above
will be added to the contract
Owner or Owner's Rep.
Spy nature,Date
1
Rejection o hange Order j Architect I
rep name and title
Reason for Rejection: Signature,Date Printed Name&Title
1VLONZWFR.T.7CTT.ONr
421 Gold Medal Court*Longwood,Florida 32750
Phone: 407.831 6275•Fax 407.332.5311
Change Order Request No.#54
Jenkins Community Center
Date 2114113
To Ajax Building Corporation
From Mark Construction
Description of Work P R #19
Keying and Core Credit
DESCRIPTION QUANT UNIT SUB SUBCONT MATRMATERIAL LABR LABOR TOTAL
U.P U P U.P
A G Mauro(See Attached Quote) -1 LS 610 $ (610) 0 $ - 0 $ - $ (610)
0 0 $ - 0 $ - 0 $ - $ -
SUB-TOTALS $ (610) $ - $ - $ (610)
SALES TAXES 7 PERCENT $ - $ _
LABOR BURDEN 42 PERCENT $ - $ -
I TOTAL CHANGE ORDER NUMBER 54 $ (810)1
The additional work requires 0 days to be added to the contract time
Acceptance of Change Order
Our signature below represents our agreement to proceed with the described work for the amount and durations as listed above
Mark Construction Co.
Ron Bryan,Project Manager
Your signature below authorizes Mark Construction Co to proceed with the above additional work,the additional days and dollar amounts listed above
will be added to the contract
Owner or Owner's Rep
Signature,Date
Rejection of Change Order I Architect
rep name and title
Reason for Rejection: Signature,Data Prnted Name&Title
MILISIITITYCILTION
Napirylirqprifilli
421 Gold Medal Court•Longwood,Florida 32750
Phone. 407.831.6276•Fax: 407.332.6319
Change Order Request No.#57
Jenkins Community Center
Date 3111/13
To Ajax Building Corporation
From Mark Construction
Description of Work.
ODP Contract adjustment
DESCRIPTION QUANT UNIT SUB SUBCONT MATF LABR LABOR TOTAL
UP. UP UP
New ODP's 1 LS -4E+05 $ (371,764 2) 0 0 $ - $ (371,764 20)
Includes 2013 0030,0083,0085,0017,0032,and 0084
Closed-Out 1 Unused ODP's 1 LS 17258 $ 17,258 03 0 0 $ - $ 17,258 03
2012.0043,0045,0051,0050,0053,0059,0056,0060,0030,&0085
SUB-TOTALS $ (354,506 2) $ - $ (354,506 17)
SALES TAXES 7 PERCENT $ -
LABOR BURDEN 42 PERCENT $ - $ -
TOTAL CHANGE ORDER NUMBER 55 $ (364,608.17)
e a.•itiona wor requires • •ays o •e a••e• tot a contract time
Acceptance of Change Order
Our signature below represents our agreement to proceed with the described work for the amount and durations as listed above
Mark Construction Co.
Ron Bryan,Project Manager
Your signature below authorizes Mark Construction Co to proceed with the above additional work,the additional days and dollar amounts listed above
will be added to the contract
Owner or Owner's Rep.
Signature,Date
Rejection of Change Order 'Architect
rep name and title
Reason for Rejection: Signature,Date Printed Name&Title
�JM
C@MPeY�IT�it
421 Gold Medal Court•Longwood,Florida 32750
Phone: 407.831.6275•Fax 407.332.5311
Change Order Request No.#29
Jenkins Community Center
Date 10/30/12
To Ajax Building Corporation
From.Mark Construction
Description of Work'Proposal Request#11
Removal of Fire Line Valve Line had to be re-tested after removal
DESCRIPTION QUANT UNIT SUB SUBCONT MATRVIATERIAL LABR LABOR TOTAL
UP UP UP
Removal of Fire Line Valve and Re-test Pipe 1 LS 3722 $ 3,722 0 $ - 0 $I$1,135_86 3172
(see attached quote)
$250 00 1
Valve will be turned over to city.
See attached letter regarding POV
to 0 $ - 0 $ - 0 $ - $ -
SUB-TOTALS $ 3,722 $ - L$1,385 86 ] 3,7J•
SALES TAXES 7 PERCENT $ - $
LABOR BURDEN 42 PERCENT $1,385 86
SUB-TOTAL
BUILDERS RISK $ 2 1 O
PERFORMANCE BOND $ 16.66
SUB-TOTAL $1,404.62
O.H &PROFIT 10 PERCENT $ 140.46
TOTAL CHANGE ORDER NUMBER 29 $1,545 08 �r
The additional work requires 0 days to be added to the contract time, 4
Acceptance of Change Order
Our signature below represents our agreement to proceed with the descnbed work for the amount and durations as listed above
Mark Construction Co.
Ron Bryan,Project Manager
Your signature below authorizes Mark Construction Co to proceed with the above additional work,the additional days and dollar amounts listed above
will be added to the contract
Owner or Owner's Rep.
Signature,Date
Rejection of Change Order I Architect
rep name and title
Reason for Rejection' Signature,Date Pnnted Name&Title
, ,
MARK
rwrr.rr.
421 Gold Medal Court"Longwood,Florida 32760
Phone: 407.831 6275•Fax: 407.332.5311
Change Order Request No.#30
Jenkins Community Center
Date:10/31/12
To Ajax Building Corporation
From Mark Construction
Description of Work.
Installation on one additional spnnkler head In the veranda per the architects request
This Is not a fire marshall request therefore drawings will be as-builted per the attached plans
DESCRIPTION QUANT UNIT SUB SUBCONT MATRMATERIAL LABR LABOR TOTAL
UP. UP UP
Sullivan Fire(see attached quote) 1 LS 728 $ 728 0 $ - 0 $ - $ 728
0 0 $ - 0 $ - 0 $ - $ -
SUB-TOTALS $ 728 $ - $ - $ 728
SALES TAXES 7 PERCENT $ - $ -
LABOR BURDEN 42 PERCENT $ - $ -
SUB-TOTAL $ 728
BUILDERS RISK $ 1
PERFORMANCE BOND $ 9
SUB-TOTAL $ 738
O H &PROFIT 10 PERCENT $ 74
I TOTAL CHANGE ORDER NUMBER 30 $ 812 I
The additional work requires 0 days to be added to the contract time
Acceptance of Change Order
Our signature below represents our agreement to proceed with the described work for the amount and durations as listed above
Mark Construction Co
Ron Bryan,Project Manager
Your signature below authonzes Mark Construction Co to proceed with the above additional work,the additional days and dollar amounts listed above
will be added to the contract
Owner or Owners Rep.
Signature,Date
Rejection of Change Order I Architect
rep name and trite
Reason for Rejection: Signature,Date Pnnted Name 6 Title
AlLontotylo
421 Gold Medal Court•Longwood,Florida 32750
Phone: 407.831.8276•Fax: 407.332.5311
Change Order Request No.#31
Jenkins Community Center
Date 10/31/12
To Ajax Building Corporation
From Mark Construction
Description of Work
Request by Civil Engineer to connnect the 8"ADS Plpe,running along the foot of the retaining wall,to the new 12 HDPE Pipe
called for In PR#8,that runs along the west boundry of the property
DESCRIPTION QUANT UNIT SUB SUBCONT MATRMATERIAL LABR LABOR TOTAL
UP UP UP
Foshee Construction(see attached quote) 1 LS 1115 $ 1,115 0 $ - 0 $ - $ 1,115
0 LS 0 $ - 0 $ - 0 $ - $ -
SUB-TOTALS $ 1,115 $ - $ - $ 1,115
SALES TAXES 7 PERCENT $ - $ -
LABOR BURDEN 42 PERCENT $ - $ -
SUB-TOTAL $ 1,115
BUILDERS RISK $ 2
PERFORMANCE BOND $ 13
SUB-TOTAL $ 1,130
O H &PROFIT 10 PERCENT $ 113
l TOTAL CHANGE ORDER NUMBER 31 $ 1,243 1
The additional work requires 0 days to be added to the contract time
Acceptance of Change Order
Our signature below represents our agreement to proceed with the described work for the amount and durations as listed above
Mark Construction Co.
Ron Bryan,Project Manager
Your signature below authorizes Mark Construction Co to proceed with the above additional work,the additional days and dollar amounts listed above
will be added to the contract
Owner or Owner's Rep.
Signature,Date
Rejection of Change Order 'Architect
rep name and title
Reason for Rejection: Signature,Data Pnntea Name&Title
uaric
ai nwrtatir
421 Gold Medal Court•Longwood,Florida 32750
Phone: 407.831 6275•Fax: 407.332 6311
Change Order Request No.#33
Jenkins Community Center
Date 10/31/12 Revised 2/14/2013
To Ajax Building Corporation
From.Mark Construction
Description of Work P R 12
Work required to regrade earthwork per PR 412.Due to the revised grade, areas of the wall originally below grade will be exposed
and is coated with waterproofing matenal that cannot be removed Due to the slope pinned Sod has been included to protect work
DESCRIPTION QUANT UNIT SUB SUBCONT MATRVIATERIAI LABR LABOR TOTAL
U P U.P U.P
Handgrading 6 HRS 23 33 $ 140 0 $ - 0 $ - $ 140
Credit for deleted Sidewalk -40 SF 3 5 $ (140) 0 $ - 0 $ - $ (140)
SUB-TOTALS $ (0) $ - $ - $ (0)
SALES TAXES 7 PERCENT $ - $ -
LABOR BURDEN 42 PERCENT $ - $ -
SUB-TOTAL $ (0)
BUILDERS RISK $ (0)
PERFORMANCE BOND $ (0)
SUB-TOTAL $ (0)
O H &PROFIT 10 PERCENT $ (0)
I TOTAL CHANGE ORDER NUMBER 33 $ (0)I
The additional work requires 0 days to be added to the contract time
Acceptance of Change Order
Our signature below represents our agreement to proceed with the descnbed work for the amount and durations as listed above
Mark Construction Co.
Ron Bryan,Project Manager
Your signature below authorizes Mark Construction Co to proceed with the above additional work,the addibonal days and dollar amounts listed above
will be added to the contract
Owner or Owner's Rep
Signature,Date
Rejection of Change Order 'Architect
rep name and bile
Reason for Rejection: Signature,Date Printed Name&Title
C�TA7 P
svrNa;N
421 Gold Medal Court•Longwood,Florida 32750
Phone: 407.831.6275•Fax. 407.332.5311
Change Order Request No.#34
Jenkins Community Center
Date 10/31/12
To Ajax Building Corporation
From Mark Construction
Descnptlon of Work RFI#62
Changed Electrical Power requirement for Well Pump requiring a 40 amp 3 phase service
DESCRIPTION QUANT UNIT SUB SUBCONT MATRMATERIALLABR LABOR TOTAL
U.P. U.P U P
4Evolutlon• Added 3 phase 40 amp Breaker 1 LS 1978 $ 1,978 0 $ - 0 $ - $ 1,978
0 0 $ - 0 $ - 0 $ - $
SUB-TOTALS $ 1,978 $ - $ - $ 1,978
SALES TAXES 7 PERCENT $ - $ -
LABOR BURDEN 42 PERCENT $ - $ -
SUB-TOTAL $ 1,978
BUILDERS RISK $ 3
PERFORMANCE BOND ® $ 24
SUB-TOTAL $ 2,005
O H &PROFIT 10 PERCENT $ 200
I TOTAL CHANGE ORDER NUMBER 34 $ 2,205 I
The additional work requires 0 days to be added to the contract time
Acceptance of Change Order
Our signature below represents our agreement to proceed with the descnbed work for the amount and durations as listed above
Mark Construction Co.
Ron Bryan,Project Manager
Your signature below authorizes Mark Construction Co to proceed with the above additional work,the additional days and dollar amounts listed above
will be added to the contract
Owner or Owners Rep.
Signature,Date
Rejection of Change Order Architect
- rep name and title
Reason for Rejection. Signature,Date Printed Name&Title
AILIONTarriarar/Crlq
421 Gold Medal Court•Longwood,Florida 32750
Phone: 407 831.6275•Fax. 407.332 5311
Change Order Request No.#36
Jenkins Community Center
Date.10/31/12
To Ajax Building Corporation
From.Mark Construction
Descnption of Work
Additional Survey work required to create survey alignment as plans did not match up with drawings,and controls
were not provided This work was coordinated with CPH to minimize added survey time.
DESCRIPTION QUANT UNIT SUB SUBCONT MATRVIATERIAL LABR LABOR TOTAL
UP. UP UP
Added surveying to establish control 16 HRS 82 5 $ 1,320 0 $ - 0 $ - $ 1,320
1 LS 0 $ - 0 $ - 0 $ - $ -
SUB-TOTALS $ 1,320 $ - $ - $ 1,320
SALES TAXES 7 PERCENT $ - $ -
LABOR BURDEN 42 PERCENT $ - $ -
SUB-TOTAL $ 1,320
BUILDERS RISK $ 2
PERFORMANCE BOND $ 16
SUB-TOTAL $ 1,338
O H &PROFIT 10 PERCENT $ 134
[TOTAL CHANGE ORDER NUMBER 36 $ 1,472
The additional work requires 2 days to be added to the contract time
Acceptance of Change Order
Our signature below represents our agreement to proceed with the described work for the amount and durations as listed above
Mark Construction Co.
Ron Bryan,Project Manager
Your signature below authorizes Mark Construction Co to proceed with the above additional work,the additional days end dollar amounts listed above
will be added to the contract
Owner or Owner's Rep.
Signature,Date
Rejection of Change Order 'Architect
rep name and title
Reason for Rejection: Signature,Date Printed Name&Tittle
•
AUILIIIKrntn*.i�u.u■i.
421 Gold Medal Court•Longwood,Florida 32750
Phone: 407.831.5275*Fax: 407.332.5311
Change Order Request No.#37
Jenkins Community Center
Date 11/27/12
To- Ajax Building Corporation
From Mark Construction
Description of Work Asi#1 Partial Request
Requesting payment for the replacement of Door 112 as requested under ASI#1 This door was orderd Immediately after the
receipt of ASI#1 and delivered prior to receipt of ASI#1 R We could not return the door See attached timeline
DESCRIPTION QUANT UNIT SUB SUBCONT MATRMATERIALLABR LABOR TOTAL
U.P U P U P
A_G Mauro Modification to Door 112 1 LS 0 $ - 2960 $ 2,960 0 $ - $ 2,960
0 LS 0 $ - 0 $ - 0 $ - $ -
SUB-TOTALS $ - $ 2,980 $ - $ 2,960
SALES TAXES 7 PERCENT $ 207 $ 207
LABOR BURDEN 42 PERCENT $ - $ -
SUB-TOTAL $ 3,167
BUILDERS RISK $ 5
PERFORMANCE BOND $ 38
SUB-TOTAL $ 3,210
O H &PROFIT 10 PERCENT $ 321
TOTAL CHANGE ORDER NUMBER 37 $ 3,531 I
The additional work requires 0 days to be added to the contract time
Acceptance of Change Order
Our signature below represents our agreement to proceed with the described work for the amount and durations as listed above
Mark Construction Co.
Ron Bryan,Project Manager
Your signature below authorizes Mark Construction Co to proceed with the above additional work,the additional days and dollar amounts listed above
will be added to the contract
Owner or Owners Rep
Signature,Date
/Rejection of Change Order 'Architect
rep name and title
Reason for Rejection: Signature,Date Pnnted Name&Title
MIRK
_ rerta��
421 Gold Medal Court•Longwood,Florida 32750
Phone: 407.831.6275•Fax. 407 332.5311
Change Order Request No.#38
Jenkins Community Center
Date.11/28/12
To Ajax Building Corporation
From,Mark Construction
Descnption of Work ASI#11 R2
Modification to Storefront door systems converting door 100A from a double to a single door with srdeiites
DESCRIPTION QUANT UNIT SUB SUBCONT MATRUATERIAL LABR LABOR TOTAL
UP U.P UP
Alliance See Attached Quote 1 LS 3650 $ 3,650 0 $ - 0 $ - $ 3,650
Materials from B B wll be turned over as requested
0 LS 0 $ - 0 $ - 0 $ - $ -
■
SUB-TOTALS $ 3,650 $ - $ - $ 3,650
SALES TAXES 7 PERCENT $ - $ -
LABOR BURDEN 42 PERCENT $ - $ -
SUB-TOTAL $ 3,650
BUILDERS RISK $ 5
PERFORMANCE BOND $ 44
SUB-TOTAL $ 3,699
O H &PROFIT 10 PERCENT $ 370
TOTAL CHANGE ORDER NUMBER 38 $ 4,069 I
The additional work days required to be added to the contract time T B 0
Acceptance of Change Order
Our signature below represents our agreement to proceed with the described work for the amount and durations as listed above
Mark Construction Co
Ron Bryan,Project Manager
Your signature below authorizes Mark Construction Co to proceed with the above additional work,the additional days and dollar amounts listed above
will be added to the contract
Owner or Owner's Rep
Signature,Date
Rejection of Change Order 'Architect
rep name and bile
Reason for Rejection: Signature,Date Printed Name&Title
. .
.. MARK
:s•Irirore
eivm.ir•fsmramensimw
421 Gold Medal Court•Longwood,Florida 32760
Phone. 407.831.8275•Fax: 407.332.5311
Change Order Request No.#39
Jenkins Community Center
Date 11/28/12
To Ajax Building Corporation
From Mark Construction
Description of Work ASI#12
Addition of Kitchen Hood Insulation
DESCRIPTION QUANT UNIT SUB SUBCONT MATRIAATERIAL LABR LABOR TOTAL
U P U P U.P.
Schwenn Services See Attached Quote 1 LS 590 $ 590 0 $ - 0 $ - $ 590
0 LS 0 $ - 0 $ - 0 $ - $ -
SUB-TOTALS $ 590 $ - $ - $ 590
SALES TAXES 7 PERCENT $ - $ -
LABOR BURDEN 42 PERCENT $ - $ -
SUB-TOTAL $ 590
BUILDERS RISK $ 1
PERFORMANCE BOND $ 7
SUB-TOTAL $ 598
O.H &PROFIT 10 PERCENT $ 60
TOTAL CHANGE ORDER NUMBER SB;COR#39 1 $ 868
Thea••Itiona says to •ea••-• tot e�i contracitime TB D
Acceptance of Change Order
Our signature below represents our agreement to proceed with the described work for the amount and durations as listed above
Mark Construction Co.
Ron Bryan,Project Manager
Your signature below authorizes Mark Construction Co to proceed with the above additional work,the additional days and dollar amounts listed above
will be added to the contract
Owner or Owner's Rep
/Signature,Date
Rejection of Change Order I Architect
rep name and title
Reason for Rejection: Signature,Date Printed Name&Title
. .
INU'....141(
ri,,,,...
421 Gold Medal Court•Longwood,Florida 32750
Phone: 407.831 6275•Fax: 407 332.5311
Change Order Request No.#41
Jenkins Community Center
Date.11/28f12
To Ajax Building Corporation
From Mark Construction
Descnption of Work RFt#68
Storm work conflicting with eldsflng power pole.
Added cost includes work to relocate storm drain around Utility Pole and the addition of one yard drain
DESCRIPTION QUANT UNIT SUB. SUBCONT MATRVIATERIAL LABR LABOR TOTAL
U.P. U.P U.P
Foshee Reroute Storm Conflict 1 LS 1668 $ 1,668 0 $ - 0 $ - $ 1,668
0 0 $ - 0 $ - 0 $ - $ -
0 0 $ - 0 $ - 0 $ - $ -
SUB-TOTALS $ 1,668 $ - $ - $ 1,668
SALES TAXES 7 PERCENT $ - $ -
LABOR BURDEN 42 PERCENT $ - $ -
SUB-TOTAL $ 1,668
BUILDERS RISK $ 3
PERFORMANCE BOND $ 20
SUB-TOTAL $ 1,691
O H &PROFIT 10 PERCENT $ 169
I TOTAL CHANGE ORDER NUMBER 41 $ 1,860 I
The additional days to be added to the contract time. T B D
Acceptance of Change Order
Our signature below represents our agreement to proceed with the descnbed work for the amount and durations as listed above
Mark Construction Co.
Ron Bryan,Project Manager
Your signature below authorizes Mark Construction Co to proceed with the above additional work,the additional days and dollar amounts listed above
will be added to the contract
Owner or Owners Rep
Signature,Date
Rejection of Change Order 'Architect
rep name and title
Reason for Rejection: Signature,Date Printed Name&Title
M4RK
TItUil"ION
oAirh.r.ry .,
421 Gold Medal Court*Longwood,Florida 32750
Phone: 407.831.6276"Fax: 407.332.6311
Change Order Request No.#42
Jenkins Community Center
Date:1/1812013
To: Ajax Building Corporation
From:Mark Construction
Description of Work
Added Tactile Warning added due to CIO Modifications
Addtion of 11 SF
DESCRIPTION QUANT UNIT SUB. SUBCONT MATRMATERIAI LABR LABOR TOTAL
U.P. U.P U.P.
Magruder:Added Tactile Warning(see attached) 1 LS 233 $ 233 0 $ - 0 $ - $ 233
1 LS 0 $ - 0 $ - 0 $ - $ -
SUB-TOTALS $ 233 $ - $ - 5 233
SALES TAXES 7 PERCENT $ - $ -
LABOR BURDEN 42 PERCENT $ - $
SUB TOTAL $ 233
BUILDERS RISK $ 0
PERFORMANCE BOND $ 3
SUB-TOTAL $ 238
O.H. &PROFIT w�� ^. _ 10 PERCENT $ 24
TOTAL CHANGE ORDER NUMBER 42 $ 280
The a t one wor requ res days to be a e O a contract t me.
Acceptance Ch na ge Order
Our signature below represents our agreement to proceed with the described work for the amount and durations as listed above.
Mark Construction Co.
Ron Bryan,Project Manager
Your signature below authorizes Mark Construction Co to proceed with the above eddltlonol work,the additional days and dollar amounts hated above
will be added to the contract
Owner or Owner's Rep.
nature Date ,1.0■0r....
Rejection of Change Order i Architect
rep.name and title
Reason for Rejection: Signature,Date Printed Name&Tale
ICON CIMPAN'Y N
421 Gold Medal Court*Longwood,Florida 32760
Phone: 407.831.8275"Fax: 407.332.5311
Change Order Request No.#43
Jenkins Community Center
Date 12/28/12 modified 1/17/13
To: Ajax Building Corporation
From:Mark Construction
Description of Work•Revisions to the Intersection of Lake and Desoto.
Includes RF1#7,ASI#15 and RFI#76
Work includes delays from Nov 20 thur Dec 24.
DESCRIPTION QUANT UNIT SUB SUBCONT MATRUATERIA1 LABR LABOR TOTAL
U.P. U.P U.P. ll
Foshee Construction(sea Attached Quote) 1 LS 17136 $ 17,136 0 $ - 0 $ - t349�36
1 SF $ - 0 $ - 0 $ - $
1 SF 0 $ - 0 $ - 0 $ - $ -
1 LS 0 $ - 0 $ - 0 $ - $ -
SUB-TOTALS
$ 17,136 $ - $ - $ 3,4906 SALES TAXES 7 PERCENT $ $ _
LABOR BURDEN 42 PERCENT - .
$ 3,489 541
SUB TOTAL $ 5 16!
17,136
BUILDERS RISK 226 06
$ 40 90
PERFORMANCE BOND $ 3,440 90 17,\206
SUB-TOTAL $ 344 85 1, '7
O H. &PROFIT 10 PERCENT
TOTAL CHANGE ORDER NUMBER 43 $ 3,890.46 19,10,
I
The additional work requires 35 days to be added to the contract time.
At the time of this delay,the offsite work was on the critical path,thur inpacting the job completion date.Added costs
for general conditions will not be included at this time,but will be reviewed upon the completion of the project.
Acceptance of Change 0 .er
Our signature below represents our agreement to proceed with the described work for the amount and durations as listed above
Mark Construction Co.
Ron Bryan,Project Manager -----
Your signature below authorizes Mark Construction Ca to proceed with the above additional work,the additional days and dollar amounts listed above
will be added to the contract
Owner or Owners Rep.
Si nature Date ...Inoniort
Rejec�tioOnofChange Order -Architect
rep name and title
Reason for Rejection: Signature,Date Printed Name&Title
• .
A/LARK
BTernarn 7OK
on� rtr►rY'
421 Gold Medal Court•Longwood,Florida 32750
Phone: 407.831.6275*Fax: 407.332.5311
Change Order Request No.#55
Jenkins Community Center
Date 3!1212013
To Nat Building Corporation
From Mark Construction
Description of Work PR#20
Provide credits to the City fo the Reimbursement of Threshold Re-Inspections as defined in the attached PR#20
DESCRIPTION QUANT UNIT SUB SUBCONT MATRMATERIAL LABR LABOR TOTAL
U P U P LIP.
Credit for Threshold Re-Inspections 1 LS -1468 $ (1,468) 0 $ - 0 $ - $ (1,468)
1 SF 0 $ - 0 $ - 0 $ - $
1 SF 0 $ - 0 $ - 0 $ - $ -
1 LS 0 $ - 0 $ - 0 $ - $
■
SUB-TOTALS $ (1,468) $ - $ - $ (1,468)
SALES TAXES 7 PERCENT $ - $
LABOR BURDEN 42 PERCENT $ - $ -
I TOTAL CHANGE ORDER NUMBER 55 $ (1,488)1
The additional work requires 0 days to be added to the contract time.
Acceptance of Change Order
Our signature below represents our agreement to proceed with the described work for the amount and durations as listed above
Mark Construction Co.
Ron Bryan,Project Manager
Your signature below authorizes Mark Construction Co to proceed with the above additional work,the additional days and dollar amounts listed above
will be added to the contract
Owner or Owner's Rep.
Signature,Date
Rejection of Change Order I Architect
rep name and title
Reason for Rejection. Signature,Date Printed Name&Title
Mark Smith
From: Gary Burton <gburton @bbmstructural.com>
Sent: Tuesday, October 23, 2012 4.00 PM
To: Mark Smith
Cc: Bora Erbilen
Subject: Jenkins
re-inspections
Total re-inspections due to failed first time inspections= $793 +$675 =$1,468 (three inspections—the
contractor called us or informed us at the field when he would do the repair)
First failed inspection when all the additional lifting rebar was omitted in all tilt-up panels and we re-inspected
the next day($675).
Second failed inspection when the contractor called for final steel inspection and he had 8 failed items that we
recorded them on the SI log. He called for two inspections on the same day, but eventually he could not fix all
the items on the same day so we had to go on another day(that he called us for)and he managed to fix the
rest of the items ($793)
actual needed inspections (additional)
I am estimating 3—4 inspections left which will be about$2,475(these inspections are (1)due to required
reinspection and (2-3)due to the contractors construction schedule modified at project's inception.
Total inspections not including the re-inspections:
$6,342.25
Total billed including the re-inspections:
$7,810.25
Therefore,with the inspections remaining,the total amount would be$ 10,285.00.
Hopefully this sorts it all out....please call if you need anything further.
Thanks so much for your help with this
GARY L.BURTON,P.E.,SECB
PRESIDENT
B■B■M
STRUCTURAL ENGINEERS
Longwood • Boca Raton • Cornelia,GA
1912 Boothe Circle• Suite 100• Longwood,FL 32750
p: 407•645•3423 ext 24
f: 407•645•3790
3998 FAU BouleN and Suite 309• Boca Raton,FL 33431
p: 561 •750• 1916
f• 561 •750• 1918
1
a owrr3r�'..w
421 Gold Medal Court•Longwood,Florida 32750
Phone: 407.831.6275•Fax: 407.332.5311
Change Order Request No.#55
Jenkins Community Center
Date.3/12/2013
To. Ajax Budding Corporation
From'Mark Construction
Descnption of Work.PR#20
Provide credits to the City fo the Reimbursement of Threshold Re-Inspections as defined in the attached PR#20
DESCRIPTION QUANT UNIT SUB SUBCONT MATRMATERIAL LABR LABOR TOTAL
UP. UP UP.
Credit for Threshold Re-Inspections 1 LS -1468 $ (1,468) 0 $ - 0 $ - $ (1,466)
1 SF 0 $ - 0 $ - 0 $ - $ -
1 SF 0 $ - 0 $ - 0 $ - $
1 LS 0 $ - 0 $ - 0 $ - $ -
SUB-TOTALS $ (1,468) $ - $ - $ (1,468)
SALES TAXES 7 PERCENT $ - $
LABOR BURDEN 42 PERCENT $ - $ -
TOTAL CHANGE ORDER NUMBER 55 $ (1,468)1
The additional work requires 0 days to be added to the contract time.
1 .Acceptance of Change Order
Our signature below represents our agreement to proceed with the described work for the amount and durations as listed above
Mark Construction Co.
Ron Bryan,Project Manager
Your signature below authonzes Mark Construction Co.to proceed with the above additional work,the additional days and dollar amounts listed above
will be added to the contract
Owner or Owner's Rep.
Signature,Date
Rejection of Change Order 'Architect
rep.name and title
Reason for Rejection: Signature,Date Printed Name&Title
s •
im R K
8'at�tUCFION
M/1\NYt ■1•1111•1
421 Gold Medal Court•Longwood,Florida 32750
Phone: 407.831.6275•Fax. 407.332.5311
Change Order Request No.#57
Jenkins Community Center
Date 3/11/13
To Ajax Building Corporation
From Mark Construction
Description of Work.
ODP Contract adjustment
DESCRIPTION QUANT UNIT SUB SUBCONT MATF LABR LABOR TOTAL
U.P. U P U P. I)
New ODP's 1 LS -4E+05 $ (371,764 2) 0 0 $ - $ (371,764.20)
Includes 2013.0030,0083,0085,0017,0032,and 0084
Closed-Out/Unused ODP's 1 LS 17258 $ 17,258.03 0 0 $ - $ 17,258.03
2012 0043,0045,0051,0050,0053,0059,0056,0060,0030,&0085
SUB-TOTALS $ (354,506 2) $ - $ (354,506 17)
SALES TAXES 7 PERCENT $
LABOR BURDEN 42 PERCENT $ - $ -
TOTAL CHANGE ORDER NUMBER 55 $ (354,506.171
The additional work requires 0 days to be added to the contract time
Acceptance of Change Order
Our signature below represents our agreement to proceed with the descnbed work for the amount and durations as listed above
Mark Construction Co.
Ron Bryan,Project Manager
Your signature below authorizes Mark Construction Co to proceed with the above additional work,the additional days and dollar amounts listed above
will be added to the contract
Owner or Owner's Rep
Signature,Date
Rejection of Change Order I Architect
rep name and title
Reason for Rejection. Signature,Date Printed Name&Title
CITY OF CLERMONT
Office of the City Clerk
April 11,2013
Mark Construction
Ron Bryan, Project Manager
471 Gold Medal Court
Longwood, FL 32750
Dear Mr. Bryan:
The Clermont City Council approved the attached at their regular meeting held on March 26,2013.
Enclosed are two original agreements requiring execution. Please retain one original for your records
and return one fully executed document to the City of Clermont, Office of the City Clerk, 685 W.
Montrose Street, Clermont, FL 34711. A self-addressed stamped envelope is enclosed for your
convenience.
Sincerely,
/ > I
/
Tracy Ackroyd, MMC
City Clerk
P O BOX 120219 • CLERMONT, FLORIDA 3471 2-021 9
PHONE 352/241-7330 • FAX 352/394-2379