2010-88 MARBEK Construction Co.
614 E. Hwy 50 Ste 324 Phone 407-468-8378/Fax 352-242-1081 Clermont, Fla. 34711
TO: City of Clermont PROJECT: Train Depot Renovation
ATTN. Mr.Wayne Saunders PROPOSAL NO. 2
FROM: Rick A. Marchand DATE: 5/11/2010
WORK PROPOSED.
Framing material and labor to wrap exposed beams and columns not originally
indicated on drawings as requested by the owner.
TOTAL COST OF PROPOSED CHANGE(ADD) $9,366.00
CALENDER DAYS EXTENSION OF TIME
The Prompt approval or rejection of this proposal is requested so that materials may be
purchased if required and the change may be incorporated into the scope of the work.
If this proposal is not returned to MARBEK Construction Co.within(7)
seven working days from the date • ' sua -, the proposal shall be considered
rejected and the work shall pr•« ed per the ..•ntract plans and specifications.
Signatures in the spaces belo indicate you,intent to issu- - change order to the
contract in the amount sho above.
Marbek = - 'o3 Co./
date 5/11/2010
Ric' A. Marchand
date 7/V072g
City of Clermont
Framing Column&Beam Wraps
Keith 60 hrs $36.25 $2,175.00
Scott 60 hrs $14.50 $870.00
T&G siding 1600 If $1.05 $1,674.40
Plywood 8 shts $44.00 $352.00
Spruce 1 " 10 1440 If $0.95 $1,368.00
1"-x 4"trim 32 If $0.30 $9.60
2"x 4" P.T. 40 If $0.42 $16.80
Chair Rail 48 If $1.35 $64.80
$6,530.60
MARBEK CONSTRUCTION CO.
PROPOSED CHANGE SUMMARY
DATE: 5/11/2010 P.C. NUMBER 2
DESCRIPTION: Beam and Column Wraps
SUBCONTRACTORS
$0.00
$0.00 $0.00
EQUIPMENT/MATERIALS
MISC as outlined $3,485.60
$0.00
$0.00
$0.00
SUBTOTAL $3,485.60
SALES TAX @ 7% $243.99
$3,729 59 $3,729.59
LABOR
SUPERVISION/MASTER CARP $2,175.00
CARPENTER $0.00
LABORER $870.00
SUBTOTAL $3,045.00
LABOR BURDEN @ 45% $1,370.25
$4,415.25 $4,415.25
ADMINISTRATIVE
ESTIMATING $0.00
GEN COND. $0.00
AS-BUILTS
$0 00• $0.00
SUBTOTAL $8,144.84
OVERHEAD&PROFIT $1,221.73
TOTAL $9,366.57