2010-89 MARBEK Construction Co.
614 E. Hwy 50 Ste 324 Phone 407-468-8378/Fax 352-242-1081 Clermont, Fla. 34711
TO: City of Clermont PROJECT: Train Depot Renovation
ATTN: Mr. Wayne Saunders PROPOSAL NO: 3 REV
FROM: Rick A Marchand DATE: 5/24/2010
WORK PROPOSED:
Structural demolition and refabrication of front porch beams in accordacne with sketches
provided by Gatorsktch Architects.
TOTAL COST OF PROPOSED CHANGE(ADD) $15,607.00
CALENDER DAYS EXTENSION OF TIME
The Prompt approval or rejection of this proposal is requested so that materials may be
purchased if required and the change may be incorporated into the scope of the work.
If this proposal is not returned to MARBEK Construction Co.within(7)
seven working days from the date of issuance, the proposal shall be considered
rejected and the work shall proceed •,- e co ract plans and specifications.
Signatures in the spaces below in.' -te your intent to issue a chap•- order to the
contract in the amount shown a••ve.
Marbek C. ftru- I'• /
��
date 5/24/2010
R_
A. Marchand
date VaAelAb
City of Clermont
MARBEK CONSTRUCTION CO.
PROPOSED CHANGE SUMMARY
DATE: 5/11/2010 P.C. NUMBER 3
DESCRIPTION. Front Porch Structural Repairs
SUBCONTRACTORS
$0.00
$0.00 $0.00
EQUIPMENT/MATERIALS
CBS Bldrs Mat Quote $4,203.48
Waco Scaffolding $1,040.00
United Rental(Lifts/Core Drill) $400.00
Misc Fastners, grout, epoxy $400.00
SUBTOTAL $6,043.48
SALES TAX @ 7% $423.04
$6,466.52 $6,466.52
LABOR
SUPERVISION/MASTER CARP $2,900.00
CARPENTER $2,000.00
LABORER $0.00
SUBTOTAL $4,900.00
LABOR BURDEN @ 45% $2,205.00
$7,105.00 $7,105.00
ADMINISTRATIVE
ESTIMATING $0.00
GEN COND. $0.00
AS-BUILTS
$0.00 $0.00
SUBTOTAL $13,571.52
OVERHEAD& PROFIT $2,035.73
TOTAL $15,607.25