_ Quote #: 010217-1R
---...z..7-7...-,--:- Date: 1/2/2017
T I L I T I E S Company: City of Clermont
Attention: Mark Griffin
Job Name: LS 5 Force Main
INC.
\v-
'" E-mail: Mgriffin(a)clermontfl.orq
'1"WE DO IT RIGHT"i —`-:•\!
��
CUC# 1224744
PO Box 291671-32129, Port Orange, FL 32128 _
Phone: 386-882-6200 email:danusl aC.cfl.rr.com
QYT LS 5 Force Main Replacement Price TOTAL
880 Furnish&Install 6"HDPE SDR-11 pipe and fittings $44.40 $39,072.00
16 Fusion time for 6"HDPE pipe 40'joints $150.00 . $2,400.00
80 Furnish&install 6"Directional Drill $90.00 $7,200.00
Furnish&install Raven 405 coating,core hole,reform
1 bench $5,500.00 $5,500.00
1 Asphalt patch Col-De-Sac after force main tie in $3,517.00 $3,517.00
1 Pressure test Force Main(water provided by City) $2,400.00 $2,400.00
900 Dewatering as required to complete Installation $6.00 $5,400.00
1 Survey and red line drawings $2,750.00 $2,750.00
1640 Grout fill old 4"force main with flowable fill&concrete pu $2.50 $4,100.00
1 Restoration of disturbed areas $2,000.00 $2,000.00
TOTAL $74,339.00
Note: Permitting by others.
Water to fill force main provided by City of Clermont.
Scope of Work for Danus Utilities:
F&I 6"HDPE pipe and fittings,Directional drill under 12th St, Dewatering as required,MH coating, MH tie in,
Asphalt patch disturbed Col-De-Sac,Survey work boundaries,Provide Red Lined drawings,Grout fill old 4"FM
Terms Net 30 Days
All material is guaranteed to be as specified. All work to be completed in a workmanli e manner according to standard
practices. Any alteration or deviation from above specifications involving extra cost be executed only upo tten
orders and will become an extra charge over and above the estimate. All agreeme I ntingent upon stri • ,accidents
or delays beyond our control. This proposal is subject to acceptance within 30 da • - d is void there. : - ;t the option
of the undersigned.
Authorized Signature LA.41.164 . ,/�-