2017-097 Orlando Office
y 618 East South Street T 407.423.8398F 407.843.1070
gal consultants Suite 700
Orlando,Florida 32801
August 24, 2017
GAI Project No.A151186.06
Mr. James Kinzler, CPM, EA
Director of Capital Planning, Grants and Projects
City of Clermont
685 West Montrose Street,
Clermont, Florida 34711
Proposal for Professional Services
W. Minneola Avenue Streetscape—Limited Construction Phase Services
Clermont, Florida
Dear Mr. Kinzler:
GAI Consultants, Inc. ("GAI"or"the Consultant") is pleased to submit this Scope of Services/Fee
Proposal for Professional Services to the City of Clermont("the Client"or"City")for the above-referenced
project. This proposal reflects the anticipated Scope, and related costs for services to be provided based
on our knowledge of the project.
Project Understanding
It is our understanding that the City of Clermont had awarded a contractor for the streetscape
improvements on W. Minneola Avenue from 7th Street to 8th Street,which includes approximately 550 LF
of roadway. The surface improvements for the roadway include mill/overlay of pavement, and streetscape
improvements on the north side of the road to adhere to the proposed City streetscape concept plans.
The project will include sidewalk and separate bicycle trail/cycle track, on-street parallel parking,
landscaping and irrigation. Street lighting includes layout only and placement of conduit for future street
lighting. Utility improvements are not anticipated as a part of this project other than minor utility
adjustments.
The City has requested limited construction phase services to support the City and contractor during
construction.
Scope of Services
Based on our understanding of the project requirements/criteria provided to date by the Client, GAI will
perform the following described Scope of Services:
3.0 Civil Engineering Construction Phase Services (Base Services)
This scope assumes that a General Contractor(GC) has been selected and the contract documents will
be bid to subcontractors.
3.1 Attend a team preconstruction meeting.
3.2 Coordinate scope of services for the civil construction related testing services and review the
civil related testing reports for project compliance.
3.3 GAI will visit the site during the site construction activities for an estimated total of up to ten
(10)site visits to observe and become familiar with the progress and quality of the civil
components of work completed to determine if the work is generally being performed in
accordance with the Civil Construction Documents. GAI will ultimately provide compliance
gaiconsultants.com
Mr.James Kinzler,CPM,EA Page 2
August 24,2017
GAI Project No.A151186.06
certifications to regulatory agencies including a"Substantial Completion"and a"Final
Completion"site visit with punch lists to the Client. These site observation visits will be
coordinated with the owner, architect and contractor(OAC) meetings on-site to reduce travel
time to and from the site and to minimize cost to the Client.
GAI will not be required to make exhaustive or continuous on-site inspections/observations to
check the quality or quantity of work, to monitor work safety requirements, or to
redesign/remodel and revise construction drawings due to unknown field conditions
encountered during construction or changes to elements of the work designed by others. GAI
shall neither have control over or charge of, nor be responsible for,the construction means,
methods,techniques, sequences or procedures, or for safety precautions and programs in
connection with the work, since these are solely the Contractor's rights and responsibilities
under the contract document.
Note: Each site visit will be followed by a field report to the Client noting deviations from the
civil contract documents. However GAI shall not be responsible for the Contractor's failure to
perform the work in accordance with the requirements of the contract documents.
3.4 Review and process civil related shop drawings for project construction document
compliance. This includes up to four(4) shop drawing reviews.
3.5 GAI will respond to Requests for Information(RFIs)from the contractor or Client during
construction. This includes up to fifteen (15) RFI's.
3.6 Review and approve field changes and related contractor change order requests. This
includes up to four(4)field changes and related change order requests.
3.7 Review inspection and TV reports and logs provided by the contractor for the civil related
components, i.e. water, sewer, storm sewer, etc.
3.8 Review and provide one set of comments to the Contractor for the As-Builts provided by the
Contractor.The As-Builts are required to be signed and sealed by a registered Land
Surveyor. GAI will review the As-Builts, and coordinate with the Contractor to provide the
level of detail necessary for the Engineer of Record's certification.
GAI will not prepare Record Drawings unless requested by the Client or the City in which
Record Drawings will be deemed additional services.
3.9 Based on the above noted site observations, reviewed reports, and supporting data provided
by the contractor, submit a"letter of General Compliance"for the civil related components of
construction to City of Clermont, if required.
4.0 Landscape Architectural Construction Phase(Base Services)
This scope assumes that a General Contractor(GC) has been selected and the contract documents will
be bid to subcontractors.
4.1 Attend a team preconstruction meeting.
4.2 GAI will visit the construction site during the site construction activities for an estimated total
of up to three(3) site visits to observe and become familiar with the progress and quality of
the landscape and irrigation components of work completed to determine if the work is
generally being performedin accordance with the Construction Documents. GAI will
ultimately provide a"Substantial Completion"and a"Final Completion"site visit with punch
lists to the Client.
GAI will not be required to make exhaustive or continuous on-site inspections/observations to
check the quality or quantity of work, to monitor work safety requirements, or to
redesign/remodel and revise construction drawings due to unknown field conditions
encountered during construction or changes to elements of the work designed by others. GAI
®2017 GAS Consultants. galconsultants.com
•
Mr.James Kinzler,CPM,EA Page 3
August 24,2017
GAI Project No.A151186.06
shall neither have control over or charge of, nor be responsible for, the construction means,
methods, techniques, sequences or procedures, or for safety precautions and programs in
connection with the work, since these are solely the Contractor's rights and responsibilities
under the contract document.
Note: Each site visit will be followed by a field report to the Client noting deviations from the
landscape contract documents. However GAI shall not be responsible for the Contractor's
failure to perform the work in accordance with the requirements of the contract documents.
4.3 Review and process landscape and irrigation related shop drawings for project construction
document compliance. This includes up to two(2)shop drawing reviews.
4.4 GAI will respond to Requests for Information (RFIs)from the contractor or Client during
construction. This includes up to five(5) RFI's.
5.0 Construction Phase Services (On-Call Services)
This task is for the scope of work during the Construction Phase above and beyond the base amount
indicated in Sections 3.0 and 4.0.All items below are included in this phase and will only be performed if
requested by the Client.
5.1 GAI will visit the site required for certifications as indicated in Sections 3.0 and 4.0.Additional
site visits as requested by the Contractor and/or Client and approved by the Client, will be
billed out at hourly rates.
5.2 GAI will respond to Requests for Information (RFIs)from the contractor or Client during
construction as indicated in Sections 3.0 and 4.0. Additional RFI's as requested by the
Contractor and/or Client and approved by the Client, will be billed out at hourly rates.
5.3 GAI will review and approve field changes'and related contractor change order requests as
indicated in Sections 3.0 and 4.0.Additional review and approvals as requested by the
Contractor and/or Client and approved by the Client,will be billed out at hourly rates.
5.4 Additional reviews and comments to the Contractor for the As-Builts will be billed at hourly
rates.
5.5 Support in reviewing Contractor Pay Requests and making recommendations for final
Certificate for Payment.
5.6 Redesign and/or remodeling and revising the construction drawings due to unknown field
conditions encountered during construction or changes to elements of the work designed by
others.
5.7 Contractor Construction Directives(CCD's)or issuance of revisions.
5.8 Attend or participate in additional OAC and team meetings/conference calls during the
Construction Phase in addition to the scope items listed in Task 3.0 providing assistance with
the civil related issues/items of the civil portion of the work.
5.9 Additional coordination or items not defined in Sections 3.0 or 4.0 will be deemed On-Call
services.
Schedule
GAI will begin work upon receipt of a copy of this Proposal executed and authorized below. GAI will
endeavor to complete its Scope of Services and deliver the project deliverables per the project schedule,
subject to excused delay occasioned by factors beyond GAI's reasonable control.
®2017 Gad Consultants. galconsultants.com
Mr.James Kinzler,CPM,EA Page 4
August 24,2017
GAI Project No.A151186.06
Compensation
Compensation for services rendered by GAI will be on a lump sum and hourly basis in accordance with
the Continuing Services Contract, General Civil and Public Facility Engineering Amendment 4, dated
February 23, 2016. The hourly tasks are not meant to be all inclusive or exhaustive and are highly
dependent on the level of effort required and/or requested by the Client.
GAI will perform the enclosed professional services for the fee summarized below.
Task Description Method of Payment Fee
3.0 Civil Engineering Construction Phase Services Lump Sum $7,000
(Base Services)
4.0 Landscape Architectural Construction Phase Lump Sum $3,800
Services(Base Services)
5.0 Construction Phase Services(On-Call Services) Hourly, as Requested Hourly
Total Estimate(less reimbursables) $10,800
Reimbursable Expenses
Reimbursable expenses may include in house and out of house projected costs required to perform and
deliver construction phase services such as postage, courier services, overnight deliveries and mileage.
Reimbursable Expenses are estimated at$500.
Reimbursable expenses will be invoiced separately on an actual cost basis.
Payment
GAI will prepare invoices monthly and payment will be due within thirty(30)days of the date of the
invoice.All other payment terms will be in accordance with the Continuing Services Contract, General
Civil and Public Facility Engineering Amendment 4, dated February 23, 2016.
Additional Services
Any services not specifically provided for in the above scope will be considered additional services.
Proposals for these additional services can be provided by GAI at the request of the Client. Additional
services we can provide include, but are not limited to, the following:
• Redesign and/or remodeling and revising the construction drawings due to unknown field
conditions encountered during construction or changes to elements of the work designed by
others.
• Preparation and/or submission for certifications to Florida Department of Environmental
Protection(FDEP)for potable water systems or sanitary sewer systems or to the St Johns River
Water Management District(SJRWMD).
• Environmental assessments/resolutions or mitigation or other services related to identification,
testing, and remediation of contaminated soils or groundwater.
• MOT design and permitting shall be provided by a licensed professional engineer as a
requirement of the selected contractor's scope of work. MOT design and permitting for contractor
phasing/logistics will be considered an additional service and is not included in this scope of
service.
• Contract Administration of Contractor's Work Program.
• NPDES NOI Permitting(to be submitted by the Contractor)
• Bid Tabulations or full CEI Services such as RFI logs, submittal logs, etc.
®2017 GAI Consultants. galconsultants.com
Mr.James Kinzler,CPM,EA Page 5
August 24,2017
GAI Project No.A151186.06
• Maintenance Guidelines.
• Contractor Construction Directives(CCDs)or issuance of revisions.
• Record Drawings and/or BIM based on the contractor's As-Builts(assumes As-Built drawings/or
BIM will be providedby the contractor).
• Certifications or construction observation other than those listed in this scope of services.
• Support in reviewing Contractor Pay Requests and making recommendations for final Certificate
for Payment.
• Value Engineering plan revisions or LEED related detailed cost analysis of alternate designs.
Assumptions and Understandings
GAI's Scope of Services, Schedule and Compensation as set forth above have been prepared on the
basis of the following assumptions and understandings:
1. GAI will utilize previously provided survey for preparation of the DD and construction plans.
2. Access to the project site(s)or other land upon which GAI is to conduct any field work will be
available to GAI'personnel in a timely manner.
3. All exploration locations will be marked and cleared by the Client for the existence of buried
utility/piping structures.
4. Client has provided,all its requirements for GAI's scope of services and all criteria and/or
specifications that GAI should utilize at the time this Proposal is authorized. This includes any
requirement for any statement of professional opinion or certification.
5. Clienthas provided all available information pertinent to GAI's scope of services, including previous
reports/drawings; utility information;topo information, etc. at the time this Proposal is authorized.
Unless otherwise noted, GAI may rely upon such information.
6. Client will give GAI prompt notice whenever it observes or otherwise becomes aware of any
development that affects the scope or timing of GAI's performance.
7. Client will examine and provide comments and/or decisions with respect to any GAI interim or final
deliverables within a period mutually agreed upon.
8. Any of Client's other consultant(s)/contractor(s)will cooperate and coordinate with GAI in a timely and
efficient manner.
9. GAI's proposed compensation and schedule are based on receipt of authorization to proceed within
thirty(30)calendardays of the date of this Proposal. GAI reserves the right to adjust its
compensation if authorization to proceed is not received within thirty(30)calendar days.
10. In the event of any claim, suit or dispute between Owner and Consultant, Owner agrees to only
pursue recovery from Consultant and will not seek recovery from, pursue or file any claim, or suit,
whether based on contract, tort including negligence, strict liability or otherwise against any director,
or employee of Consultant.
11. PERSONAL LIABILITY OF PERSONNEL DISCLAIMER - PURSUANT
TO FLORIDA STATUTE 558:0035, TO THE FULLEST EXTENT
PERMITTED-BYLAW, OWNER AGREES THAT PURSUANT TO
SECTION,-CAN INDIVIDUAL EMPLOYEE OR AGENT MAY NOT BE
HELD LIABLE FOR NEGLIGENCE.
®2017 GAI Consultants. gaiconsultants.com
Mr.James Kinzler,CPM,EA Page 6
August 24,2017
GAI Project No.A151186.06
Please do not hesitate to contact me at 321-319-3038 if you have any questions or wish to discuss this
Proposal. If this Proposal isacceptable, please sign where indicated below and return one copy for our
file. This also will serve as authorization for GAl to proceed. GAI's performance of the Scope of Services
will be governed by the GAI Standard Terms and Conditions for Professional Services, attached hereto
as Exhibit A and incorporated herein by reference.
REQUESTED AND AUTHORIZED BY:
Sincerely, City of Clermont
GAI Consultants, Inc.
BY:
PRINTED NAME:
Frank Bellomo JGN,�J 47.t 2
Senior Director, Landscape Architecture
Assistant Vice President TITLE: �i�/..
DATE: /
41110
/
Robert A. Schanck, P.E.
Senior Director of Engineering
Vice President
RAS/snr
0 2017 GAI Consultants. gaiconsultants.com