2001-15
.
.
.
,.
.
.
Document 00530 - Change Order
No.5
PROJECT: Desoto Street Drainage Improvements
DATE OF ISSUANCE: April 26, 2001
EFFECTIVE DATE: April 26, 2001
OWNER: City of Clermont
ENGINEER'S Job No: 51130.012
CONTRACTOR: Gibbs & Register, Inc.
ENGINEER: Springstead Engineering, Inc.
You are directed to make the following changes in the Contract Documents.
Description: Adjust contract time.
Reason for Change Order: Bring the project to final closeout.
Attachments: (List documents supporting change) None
CHANGE IN CONTRACT PRICE
Original Contract Price
CHANGE IN CONTRACT TIMES:
Original Contract Times
Substantial Completion: 75 Days
Ready for final payment: 75 Days
$117,854.00
Net changes from previous CO No. I to 4
$837.00
Net change from previous CO No. I to No.4
17 Days
Contract Price prior to this Change Order
Contract Times prior to this Change Order
Substantial Completion: 92 Days
Ready for final payment: 92 Days
$118,691.00
Net Decrease of this Change Order
$3,500.00
Net Increase of this Change Order
14 Days
Contract Price with all approved Change Orders
Contract Times with all approved Change Orders
Substantial Completion: 106 Days
Ready for final payment:106 Days
$115,191.00
APPROVED: ACCEP
B~Y'
er (Authorized Signature) . Contra
Q/lo/Ol
D~dL
By:
Date:
(Authorized Signature)
ø:;/, /oJ
1/
Date:
Date:
(b:\00530)
Document 00530 - Change Order