Press Alt + R to read the document text or Alt + P to download or print.
This document contains no pages.
2003-46
. .
.
.
.
I . .
SECTION 00500
AGREEMENT
THIS AGREEMENT made and entered into this _23rd- day of December 2003, by and
between the City of Clermont, Florida, (hereinafter called the OWNER) and WPC ~R)Ntw»,
Ltd. (hereinafter called CONTRACTOR); Industrial Contractors
WITNESSETH:
OWNER and CONTRACTOR, in consideration of the mutual covenants hereinafter set forth,
agree as follows:
ARTICLE 1 - SCOPE OF WORK
CONTRACTOR, as an independent CONTRACTOR, and not as an agent of the OWNER, shall
complete all Work as specified or indicated in the Contract Documents. The Work is generally
described as follows:
. Construct high service well pump buildings, sodium hypochlorite chemical feed buildings,
generator support pads, and pressure tank support pads for each site.
. Furnish and install one (1) 40,000 gallon pressure vessel and appurtenances at each site.
. Furnish and install high service well pump and appurtenances including, but not limited to,
electrical, valving and piping at each site.
. Furnish and install sodium hypochlorite bulk storage tanks, feed pumps and all required
appurtenances and piping at each site,
. Furnish and install proposed generator and fuel storage at each site.
. Complete applicable site work and restoration including, but not limited to, sodding,
mulching, paving, grading, and fencing,
The project for which the Work under the Contract Documents may be the whole or only a part is
generally described as follows:
LAKEVIEW HILLS AND SUNBURST LANE WELL SITES
CSP/slm/specs/s-6/Sunburst & Lakeview contract doc
HAI#00-007.05 00500-1
121203
'.
.
.
.
ARTICLE 2 - ENGINEER
The Project has been designed by Hartman & Associates, Inc., whose address is 201 East Pine
Street, Suite 1000, Orlando, FL 32801, who is hereinafter called ENGINEER, and who will
assume all duties and responsibilities and will have the rights and authority assigned to the
ENGINEER in the Contract Documents in connection with completion of the Work in
accordance with the Contract Documents.
ARTICLE 3 - CONTRACT TIME
3.1
"The Work shall be completed with two substantial completion dates (one for each site)
and one final completion date. The Contractor will not be able to mobilize on site until
the well driller has completed the well and has left the site, or until the City provides
permission for the General Contractor to proceed. The Work for substantial completion
of the Sunburst Lane site as described below shall be completed within one-hundred fifty
(150) days after the date when the Contract Times commence to run or when the well
drilling is complete and the well driller is off of the site. The Work for substantial
completion of the Lakeview Hills site as described shall be completed within two-
hundred ten (210) days after the date when the Contract Times commence to run or when
the well drilling is complete and the well driller is off the site. The Work for final
completion as described below shall be fully completed and ready for final payment in
accordance with Paragraph 14,13 of the General Conditions within two-hundred forty
(240) days after the date when the Contract Times commence to run.
All work associated with each site shall be 100% completed and operational prior to
substantial completion.
The following schedule is anticipated:
1.
Bid Opening:
November 14,2003
2.
Contract Award:
December 22, 2003
3.
Contract Execution and Notice to Proceed: December 23, 2003
3.2
Liquidated Damages. OWNER and CONTRACTOR recognize that TIME IS OF THE
ESSENCE of this Agreement and that OWNER will suffer financial loss if the Work is
not completed within the times specified in paragraph 3.1 above, plus any extensions
thereof allowed in accordance with Article 12 of the General Conditions, They also
recognize the delays, expense and difficulties in proving the actual loss suffered by
OWNER if the Work is not completed on time. Accordingly, instead of requiring any
such proof, OWNER and CONTRACTOR agree that as liquidated damages for delay (but
not as a penalty), CONTRACTOR shall pay OWNER one thousand dollars ($1,000.00)
for each day that expires after the time specified in paragraph 3,1 for Substantial
CSP/slm/specs/s-6/Sunburst & Lakeview contract doc
HAI#00-007.05 00500-2
121203
'.
.
.
.
I . .
Completion until the Work is substantially complete. This amount represents an estimate
of OWNER's damages for loss of use and administrative costs associated with delay,
After Substantial Completion, if CONTRACTOR shall neglect, refuse or fail to complete
the remaining Work within the time specified in paragraph 3.1 for completion and
readiness or fail to complete the remaining Work within the time specified in paragraph
3.1 for completion and readiness for final payment or any proper extension thereof
granted by OWNER, CONTRACTOR shall pay OWNER five hundred dollars ($500.00)
for each day that expires after the time specified in paragraph 3.1 for completion and
readiness for final payment. This amount represents an estimate of OWNER's damages
for loss of use and administrative and costs associated with delay. However, the
contractor shall not be entitled to additional payment for timely or early completion of the
project.
ARTICLE 4- CONTRACT PRlCE
4.1
OWNER shall pay CONTRACTOR for performance of the Work in accordance
with the Contract Documents in current funds at the lump sum or unit prices as
presented in the Bid Form, which is incorporated herein and made a part hereof by
this reference.
4.2 OWNER shall pay CONTRACTOR for completion of the Work in accordance
- with the Contract Documents an amount in current funds equal to the amount
below:
Total of all unit prices:
One Million Five Hundred Ninety-Seven Thousand Dollars
$ 1.597.000
(figures)
(use words)
4.3
The parties expressly agree that the Contract Price is a fixed stipulated sum,
except with regard to those items in the Bid, which are subject to unit prices. As
provided in paragraph 11.9 of the General Conditions estimated quantities are not
guaranteed and determinations of actual quantities and classification are to be
made by ENGINEER as provided in paragraph 9.10 of the General Conditions.
ARTICLE 5- PAYMENT PROCEDURES
5.1
CONTRACTOR shall submit Applications for Payment in accordance with the
Contract Documents. Applications for Payment will be processed by ENGINEER
as provided in the Genera~ Conditions.
5.2
Progress Payments; Retainage. Payment shall be in accordance with the City of
Clermont Code of Ordinances
CSP/slm/specs/s-6/Sunburst & Lakeview contract.doc
HAI#00-007.05 00500-3
121203
'.
.
.
.
: . .
5.3
Prior to Substantial Completion, progress payments will be made in an amount
equal to the percentage indicated below, but in each case, less the aggregate of
payments previously made and less such amounts as ENGINEER shall determine,
or OWNER may withhold, in accordance with paragraph 14.7 of the General
Conditions.
5.3.1 Ninety percent (90%) of the value of Work completed, with the balance
being retainage.
5.3.2 Ninety percent (90%), with the balance being retainage of the value of
materials and equipment not incorporated in the Work, but delivered,
suitably stored and accompanied by documentation satisfactory to
OWNER as provided in paragraph 14.2 of the General Conditions.
5,3.3 Upon Substantial Completion, the Owner may, at his option, increase total
payments to CONTRACTOR to ninety five percent (95%) of the Contract
Price, with the balance being retainage, less such amounts as ENGINEER
shall determine, or OWNER may withhold, in accordance with paragraph
14.7 of the General Conditions,
5.4
Final Payment Upon final completion of the Work in accordance with Paragraph
14.13 of the General Conditions, as supplemented, OWNER shall pay
CONTRACTOR an amount sufficient to increase total payments to one-hundred
percent (100%) of the Contract Price, However, not less than two percent (2%) of
the Contract Price shall be retained until Contract Closeout is completed as
specified in Section 01700 and all Record Drawings, specifications, addenda,
modifications and shop drawings, including all manufacturers instructional and
parts manuals are delivered to and accepted by the ENGINEER.
ARTICLE 6 - CONTRACTOR'S REPRESENTATIONS
In order to induce OWNER to enter into this Agreement, CONTRACTOR makes the following
representations:
6.1
CONTRACTOR has examined and carefully studied the Contract Documents
(including the Addenda listed in Article 7) and the other related data identified in
the Bidding Documents including "technical data."
6.2
CONTRACTOR has visited the site and become familiar with and is satisfied as
to the general, local and site conditions that may affect cost, progress,
performance or furnishing of the Work.
CSP/slm/specs/s-6/Sunburst & Lakeview contract doc
HAI#00-007,05 00500-4
121203
; " .
".
.
.
.
6.3
6.4
6.5
6.6
6.7
CONTRACTOR is familiar with and is satisfied as to all federal, state and local
Laws and Regulations that may affect cost, progress, performance and furnishing
of the Work.
CONTRACTOR has carefully studied all reports of explorations and tests of
subsurface conditions at or contiguous to the site and all drawings of physical
conditions in or relating to existing surface or subsurface str:uctures at or
contiguous to the site (except Underground Facilities) which have been identified
in the Supplementary Conditions as provided in paragraph 4,2.1 of the General
Conditions. CONTRACTOR accepts the determination set forth in paragraph SC-
4.2 of the Supplementary Conditions of the extent of the "technical data"
contained in such reports and drawings upon which CONTRACTOR is entitled to
rely as provided in paragraph 4.2 of the General Conditions. CONTRACTOR
acknowledges that such reports and drawings are not Contract Documents and
may not be complete for CONTRACTOR's purposes. CONTRACTOR
acknowledges that OWNER and ENGINEER do not assume responsibility for the
accuracy or completeness of information and data shown or indicated in the
Contract Documents with respect to Underground Facilities at or contiguous to
the site. CONTRACTOR has obtained and carefully studied (or assumes
responsibility for having done so) all such additional supplementary examinations,
investigations, explorations, tests, studies and data concerning conditions (surface,
subsurface and Underground Facilities) at or contiguous to the site or otherwise
which may affect cost, progress, performance or furnishing of the Work or which
relate to any aspect of the means, methods, techniques, sequences and procedures
of construction to be employed by CONTRACTOR and safety precautions and
programs incident thereto. CONTRACTOR does not consider that any additional
examinations, investigations, explorations, tests, studies or data are necessary for
the performance and furnishing of the Work at the Contract Price, within the
Contract Times and in accordance with the other terms and conditions of the
Contract Documents.
CONTRACTOR is aware of the general nature of Work to be performed by
OWNER and others at the site that relates to the Work as indicated in the Contract
Documents.
CONTRACTOR has correlated the information known to CONTRACTOR,
information and observations obtained from visits to the site, reports and drawings
identified in the Contract Documents and all additional examinations,
investigations, explorations, tests, studies and data with the Contract Documents.
CONTRACTOR has given ENGINEER written notice of all conflicts, errors,
ambiguities or discrepancies that CONTRACTOR has discovered in the Contract
Documents and the written resolution thereof by ENGINEER is acceptable to
CONTRACTOR, and the Contract Documents are generally sufficient to indicate
CSP/slm/specs/s-6/Sunburst & Lakeview contract doc
HAI#00-007.05 00500-5
121203
.
.
.
. : . ,
and convey understanding of all terms and conditions for performance and
furnishing of the Work.
ARTICLE 7 - CONTRACT DOCUMENTS
The Contract Documents which comprise the entire Agreement between the OWNER and
CONTRACTOR are attached to this Agreement, are made a part hereof and consist of the
following:
7.1
7,2
7.3
7.4
7.5
7.6
7.7
7.8
7.9
7.10
7.11
7.12
This Agreement (Section 00500) (pages 1 to 13, inclusive).
Exhibits to this Agreement, if any.
Performance Bond, Payment Bond and Certificates of Insurance (Sections 00610,
00620 and 00650, respectively).
Notice of Award and Notice to Proceed (Sections 00841 and 00842, respectively).
General Conditions (Section 00700) as amended by the Supplementary
Conditions.
Supplementary Conditions (Section 00800).
FDEP Supplementary Conditions (Construction).
Project Manual bearing the general title: City of Clermont, Lakeview Hills and
Sunburst Lane Well Sites and consisting of one (1) volume including Divisions 0
through 16.
Drawings consisting of a cover sheet and sheets numbers G-1 through V -3 .
Addenda numbers --L through ...l..., inclusive.
The following which may be delivered or issued after the Effective Date of the
Agreement and are not attached hereto: All Written Amendments and other
documents amending, modifying or supplementing the Contract Documents
pursuant to paragraphs 3.5 and 3.6 of the General Conditions.
Bid Form (Section 00300) (Pages 1 to 9, inclusive) and all documents attached to
and made a condition of the Bid.
There are no Contract Documents other than those listed above in this Article 7. The Contract
Documents may only be altered, amended, or repealed in accordance with Article 3 of the
General Conditions as modified in the Supplementary Conditions.
CSP/slm/specs/s-6/Sunburst & Lakeview contract doc
HAI#00-007.05 00500-6
121203
".
.
.
.
. : " ,
ARTICLE 8 - MISCELLANEOUS
8.1
OWNER and CONTRACTOR each binds himself, his partners, successors,
assigns and legal representatives to the other party hereto, his partners, successors,
assigns or legal representatives in respect to all covenants, agreements and
obligations contained in the Contract Documents.
8.2
Terms used in this Agreement, which are defined in Article 1 of the General
Conditions, shall have the meanings indicated in the General Conditions, as
modified in the Supplementary Conditions.
8.3
If any section, subsection, sentence, clause, phrase, or portion of this agreement is
for any reason held invalid or unconstitutional by any court of competent
jurisdiction, such portion shall be deemed a separate, distinct and independent
provision and such holdings shall not affect the validity of the remaining portions
thereof.
ARTICLE 9 - GOVERNING LAW
This Agreement shall be governed by the laws of the State of Florida. Both parties agree that the
courts of the State of Florida shall have jurisdiction of any claim arising in connection with this
Agreement In the event of litigation arising out of this Agreement, the prevailing party shall be
entitled to the award of attorney's fees and costs at both the trial and appellate level.
IN WITNESS WHEREOF, the parties hereto have signed this Agreement in triplicate. One
counterpart each has been delivered to OWNER, CONTRACTOR and ENGINEER. All portions
of the Contract Documents have been signed or identified by OWNER and CONTRACTOR or
identified by ENGINEER on their behalf.
CSP/slm/specs/s-6/Sunburst & Lakeview contract doc
HAI#00-007.05 00500- 7
121203
....
.
.
.
, ."
This Agreement will be effective on
, 2003
OWNER:
City of Clermont
BY:~
CONTRACTOR:
WPC ðlPVJtÖfC
Ltd
BY:
NAME: Harold S. Turville
(type)
NA
Belloit
(type)
TITLE:President of the General Partner
TITLE: Mayor
ATTEST~ V~
NAME: Jane Warren
(type)
¿
ATTEST:
'~
NAME:
Kristie Coleman
(type)
Address for giving notices:
Address for giving notices:
City of Clermont
685 W, Montrose St. 2nd Floor
Clermont. Florida 34711
WPC~~~~~~ Industrial Contracto
11651 Phillips Highway
Jacksonville. FL 32256
Approved as to form and correctness:
.2003
Florida State Contractor's
License No.: CGCO46120
END OF SECTION
CSP/slm/specs/s-6/Sunburst & Lakeview contractdoc
HAI#00-007.05 . 00500-8
121203