Contract 2024-040A CO2Docusign Envelope ID: OA91D1 F9E-DF74-4CC3-BDFB-D13D3D833447
CHANGE ORDER FORM
Contract / P.O. Number: 2024-040 / 20250596 Bid Number: RFB 24-095
Change Order Number: 2 Change Order Date: Mar 27, 2025
Project Name: Lake Winona Basin 12A Drainage Im Department: Public Services
Job Location: Lake Winona
VENDOR INFORMATION:
Company Name: DB Civil Construction, LLC.
Address: 4475 US-1 South, Suite 707 City, St., Zip: St. Agustine, FL 32086
Contact Name: John Robbins, Project Manager Telephone:386-256-7460
DESCRIPTION OF CHANGE:
Alteration, deviation, addition, or deletion caused by conditions encountered during construction not covered by the specifications and
drawings of the project (attach additional pages if necessary).
Additive Change Order: Includes the installation of a curb section to address a resident's concern, as well as the
addition of a drainage flume to direct street runoff into the newly dredged drainage channe it in the total amount of
$13,740
ITEM
AMOUNT
A.
ORIGINAL CONTRACT VALUE:
$ 378,920.00
B.
AMOUNT OF THIS CHANGE ORDER:
$ 13,740.00
Must be within the overall scope of services in accordance with contract specifications.
C.
PERCENT OF CONTRACT VALUE THIS CHANGE ORDER (B/A):
% 3.6%
D.
AMOUNT OF PREVIOUS CHANGE ORDERS:
$ 32,570.00
E.
TOTAL AMOUNT OF ALL CHANGE ORDERS (B+D):
$ 46,310.00
F.
PERCENT OF CONTRACT OF ALL CHANGE ORDERS (E/A): 10% Maximum
% 12.2%
G.
NEW CONTRACT VALUE (A+E)
$ 425,230.00
This Change Order is not valid without the following signatures:
Signed by:
�Aabw E?A�(br 4/9/2025
6907C43629284A5_.
CONTRACTOR Date PROJECT ARCHITECT / ENGINEER Date
EsDocuSigned by: lr�
Signed by:
fbin,t,� �jV1�1n,w, 4/9/2025 K& Vat (W�ln.t,� 4/9/2025
014063RAFF414OF 33260A85R04 D4AF
DEPARTMENT DIRECTOR Date PROCUREMENT DIRECTOR / Date
CITY MANAGER
Council approval is required if change order(s): 1) exceeds $49,999; 2) exceeds the greater of $100,000 OR 10% of the original
contract amount for construction projects; 3) the funds are not available in the approved budget for the department.
CITY OF CLERMONT ATTEST:
Signed by: DocuSigned by:
4/9/2025 ETAdAo� Haws 4/10/2025
2BA7692F758C492... 3AD7F34905B344A.-
MAYOR Date CITY CLERK Date
Rev. 1-1-2021
Docusign Envelope ID: OA9D1F9E-DF74-4CC3-BDFB-D13D3D833447
DB Civil Construction LLC
Pricing for Change Order - Lake Winona added Drainage Structures
To: City of Clermont Date: 2/26/2025
Project: Lake Winona 12A Basin Drainage Project
Pricing for Scope of Work
ITEM NO.
DESCRIPTION
QUANTITY
UM
UNITPRICE
TOTAL
1
SOIL TRACKING PREVENTION DEVICE
(1.00)
EA
$2,000.00
($2,000.00)
2
REGULAR EXCAVATION
68
CY
$ 100.00
$6,800.00
3
ICONCRETE DITCH PAVEMENT, NON REINFORCED, 4"
RIPRAP - RUBBLE, DITCH LINING
BEDDING STONE
Pipe Culvert 15" RCP
10
SY
$ 200.00
$2,000.00
4
6
TN
$ 500.00
$3,000.00
5
11
TN
$ 500.00
$5,500.00
6
(8.00)
LF
$195.00
TOTAL:
$13,740.00
Description Of Work:
Item No. Explanation of Change
1 Not required
2 Actual Quantity required to meet plan grading
3 Owner added additional paved Flume
4 Owner added additional paved Flume, resulting in additional riprap required. Approved in field
5 Owner added additional paved Flume, resulting in additional riprap required. Approved in field
6 Change Order No 1 Quantity was 88 LF, only 80 LF required
SUBMITED BY: John Robbins
Page 1 of 1