HomeMy WebLinkAboutContract 2023-028A CO (4)Docusign Envelope ID: 61AE9FCE-7BDA-4lC6-BCF4-3C2EDOC2A179
CHANGE ORDER FORM
Contract / P.O. Number: 2023-028 / 20235048 Bid Number: RFB 23-002
Change Order Number:9 Change Order Date: Jul 31, 2025
Project Name: East Side Water Reclamation Facility Department: Public Services
Job Location: Clermont East WRF
VENDOR INFORMATION:
Company Name: Vogel Bros. Building, Co.
Address: 2720 Drane Field Road City, St., Zip: Lakeland, FL 33811
Contact Name: Andrew Decker Telephone:(863) 646-5078
DESCRIPTION OF CHANGE:
Alteration, deviation, addition, or deletion caused by conditions encountered during construction not covered by the specifications and
drawings of the project (attach additional pages if necessary).
Additive change order in the amount of $312,628.75 to include:
1) Additional pavement request using SP12.5 (PCO #15) = $122,228.75
2) Cleaning of grit and sediment for basisn 1 thru 4 (PCO #17) = $190,400.00
See attached documents for more information.
ITEM
AMOUNT
A.
ORIGINAL CONTRACT VALUE:
$ 44,300,000
B.
AMOUNT OF THIS CHANGE ORDER:
$ 312,628.75
Must be within the overall scope of services in accordance with contract specifications.
C.
PERCENT OF CONTRACT VALUE THIS CHANGE ORDER (B/A):
% 0.7%
D.
AMOUNT OF PREVIOUS CHANGE ORDERS:
$ 153,247.34
E.
TOTAL AMOUNT OF ALL CHANGE ORDERS (B+D):
$ 465,876.09
F.
PERCENT OF CONTRACT OF ALL CHANGE ORDERS (E/A): 10% Maximum
% 1.1%
G.
NEW CONTRACT VALUE (A+E)
$ 44,765,876.09
This Change Order is not valid without the following signatures:
Ev
DocuSigned by:
Amu, Vbgl
ssrnzaas�anneae
CONTRACTOR
DocuSigned by:
8/6/2025 E
►n-�
Date PROJECT ARCHITECT / ENGINEER
8/6/2025
Date
DocuSigned by: ir�
Signed by:
fbl�,u j bVWA S6t& 8/6/2025 Vat %� r 8/6/2025
rS47'DEPARTMENT DIRECTOR Date PROCUREMENT DIRECTOR / Date
CITY MANAGER
Council approval is required if change order(s): 1) exceeds $49,999; 2) exceeds the greater of $100,000 OR 10% of the original
contract amount for construction projects; 3) the funds are not available in the approved budget for the department.
CITY OF CLERMONT ATTEST:
MAYOR Date CITY CLERK Date
Rev. 1-1-2021
Docusign Envelope ID: 61AE9FCE-7BDA-4lC6-BCF4-3C2EDOC2A179
VOWEL
B Ft O$- SU ILDI IVG CO -
better people = better builders'
PCO#15 Additional Pavement Request Using SP12.5
PROJECT: Clermont East WRF
OWNER: City of Clermont
ENG: Tetra Tech
Proposal # PCO-15
DATE: 7/14/2025
PREPARED BY: DJB
Vogel Brothers will provide all necessary labor, materials, equipment, tools and supervision required to execute the work scope defined herewith, in accordance with this proposal, for the amount listed below. This quotation contains items
only as listed herein. Any additional items not listed will be subject to additional compensation. Any additional time required to perform this work is listed herewith. Written confirmation of your acceptance is required before work can
commence.
SCOPE:
Item 1- Relocation of the Reclaimed Water Pump station per RFI#003 response requires additional 30" Ductile Iron Piping.
PROPOSAL BREAKDOWN
ITEM11
DESCRIPTION
QTY
❑
❑NI
UNITS
CREDITS
UT PRICE SUBTOTAL
ILABOR
UNIT PRICE I SUBTOTAL
MATERIAL
I UNIT PRICE I SUBTOTAL
EQUIPMENT
I UNIT PRICE SUBTOTAL
SUBCONTRACT
I:NIT PRICE SUBTOTAL
TOTAL
1
Option #2 ACPLM Quote June 5, 2025
1
LS
$
$ 5,621.00
$
$ 103,026.00
$ 103,026.00
$ 108,647.00
2
$
$
$
$
$
$
3
$
$
$
$
$
$
4
$
$
$
$
$
$
5
$
$
$
$
$
$
6
$
$
$
$
$
$
7
$
$
$
$
$
$
8
$
$
$
$
$
$
9
$
$
$
$
$
$
$
$
$
$ -
$
$
SUMM:/of
Tax @ Taxable Materials
Small T4% of Labor
SUBTODIRECT COST:
Bonds urance @ 2 % of Direct Cost
AllowedP on Subcontracted Work
AllowedP on Direct Cost
GRANAL
6.00%
400%
2.00%
10.00%
15.00%
$
$
$ 5,621.00
$
$
$ 103,026.00
$ 108,647.00
$
$ 224.84
$ 108,871.84
$ 2,177.44
$ 10,302.60
$ 876.88
$122,228.75
VBBC is requesting for the contract completion dates to bc(Increased, Deere_:_', ' `_ eve_ ge) as a result of this Change Proposal.
This quotation is valid for 30 days from this proposals date. Written Acceptance is required for this work to commence
Vogel Bros Building Co
Contractor
By:
Date:
Owner Engineer
By:
Date:
By:
Date:
Docusign Envelope ID: 61AE9FCE-7BDA-4lC6-BCF4-3C2EDOC2A179
VaG-E=.
BR,OS. BUILDING CO.
better people = better builders®
PROJECT:
OWNER:
ENG:
WORK SCOPE BREAKDOWN
Clermont East WRF
ty of Clermont
Tetra Tech
PCO#15 Additional Pavement Request Using SP12.5
Proposal # PCO-15 0
DATE: 7/14/2025
PREPARED BY: DJB
Item No. Description CITY Units Material Equipment Labor Sub
U/P Total U/P Total U/P Total U/P Total Subtotal
MATERIAL
EQUIPMENT
LABOR
1 Superintendent 1 Week $ 4,500.00 $ 4,500.00
1 Superintendent Truck 1 Week $ 750.00 $ 750.00
1 Travel / Mileage 1 Week $ 371.00 $ 371.00
SUBCONTRACT
ACPLM $ 103,026.00 $ 103,026.00 $ 103,026.00
$ $ $ 5,621.00 $ 103,026.00 $ 108,647.00
Tax @ 6% of Taxable Material: $ -
Small Tools @ 4% of Labor: $ 224.84
Subtotal Direct Cost: $ 108,871.84
Bonds and Insurance @ 2% of Direct Cost $ 2,177.44
Allowed OH &P on Subcontracted Work @10%: $ 10,302.60
Allowed OH &Pon Direct Cost @15%: $ 876.88
Total: $ 122,228.75
Docusign Envelope ID: 61AE9FCE-7BDA-4lC6-BCF4-3C2EDOC2A179
VOWEL
13 Fit, O$. SU ILDI IVG CO -
better people = better builders'
PCO#17 Basins 1 thou 4 Cleaning of Grit and Sediment
PROJECT: Clermont East WRP
OWNER: City of Clermont
ENG: Tetra Tech
Proposal # 001
DATE: 7/21/2025
PREPARED BY: DJB
Vogel Brothers and our Sub -Contractors will provide all necessary labor, materials, equipment, tools and supervision required to execute the work scope defined herewith, in accordance with this proposal, based on the estimated quantities
listed in the attached quote for amount listed below. This quotation contains items only as listed herein. Any additional quantities and or mobilizations that are required will be subject to additional compensation. Any additional time
required to perform this work is listed herewith. Written confirmation of your acceptance is required before work can commence.
SCOPE:
Item 1- SYNAGRO Cleaning of Basins 1 thou 4 per the attached quote. Vogel Bros will not be self -performing work to complete this scope of work. Vogel Bros has not included any management services for monitoring this scope of work.
PROPOSAL BREAKDOWN
F_-11
DESCRIPTION
QTY
❑❑
UNITS
CREDITS
PRIC
E CE SUBTOTAL
LABOR
UNIT PRICE I SUBTOTAL
MATERIAL
I UNIT PRICE I SUBTOTAL
EQUIPMENT
I UNIT PRICE SUBTOTAL
SUBCONTRACT
I:NIT PRICE SUBTOTAL
TOTAL
1
Removal and cleaning of Basins I thru 4
250
CY
$
$
$
$
$
$
$ 625.00
$ 156,250.00
$ 156,250.00
1
Mobilizations
2
Mobs
$
$
$
$ 6,875.00
$ 13,750.00
$ 13,750.00
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$ -
$ -
$ -
$ -
$ -
$ -
SUMM:/of
Tax @ of,
Taxable Materials
Small T4% of Labor
COST:
Bonds urance @ 2 % of Direct Cost
AllowedP on Subcontracted Work
AllowedP on Direct Cost
6.00%
400%
2.00%
10.00%
15.00%
$
$
$
$
$
$ 170,000.00
$ 170,000.00
$
$ 170,000.00
$SUBTODIRECT
$ 3,400.00
$ 17,000.00
$GRANAL $190,400.00
VBBC is requesting for the contract completion dates to bc(Increased, Deere_:_', ' `_ eve_ ge) as a result of this Change Proposal.
This quotation is valid for 30 days from this proposals date. Written Acceptance is required for this work to commence
Vogel Bros Building Co
Contractor
By:
Date:
Owner Engineer
By:
Date:
By:
Date:
Docusign Envelope ID: 61AE9FCE-7BDA-4lC6-BCF4-3C2EDOC2A179
VaGEL
BROS. BUILDING CO,
better people = better builders'
PROJECT:
OWNER:
ENG:
WORK SCOPE BREAKDOWN
Clermont East WRF
ty of Clermont
Tetra Tech
PCO#17 Basins 1 thru 4 Cleaning of Grit and Sediment
Proposal # 001 0
DATE: 7/21/2025
PREPARED BY: DJB
Item No. Description CITY Units Material Equipment Labor Sub
U/P Total U/P Total U/P Total U/P Total Subtotal
MATERIAL
EQUIPMENT
LABOR
SUBCONTRACT
1 SYNAGRO
1 SYNAGRO
250 CY
2 Mobs
$ 625.00 $ 156,250.00
$ 6,875.00 $ 13,750.00
$ - $ - $ $ 170,000.00 $170,000.00
Tax @ 6%of Taxable Material: $ -
Small Tools @ 4%of Labor: $ -
Subtotal Direct Cost: $ 170,000.00
Bonds and Insurance @ 2% of Direct Cost $ 3,400.00
Allowed OH &P on Subcontracted Work @10%: $ 17,000.00
Allowed OH &P on Direct Cost @15%: $ -
Total: $ 190,400.00